District Energy Systems

NC-2009 EAc1:Optimize energy performance
posted by  Matt Humphreys  on 

I have project that is purchasing chilled water from the local utility.

1
Mon Sep 9, 2013, 1:52 pm

Weather data for sizing runs

NC-2009 EAc1:Optimize energy performance
posted by  Francesco Passerini  on 

The equipment capacities for the baseline building design shall be based on sizing runs for each orientation (see G3.1.2.2 and G3.1.2.2.1).

0

Baseline HVAC system for a naturally ventilated Building

NC-2009 EAc1:Optimize energy performance
posted by  Jayanthi Raju Vadivelu  on 

In one of our projects, we've 100% naturally ventilated school building, which will have ceiling fans for comfort, a total area of approx 80,000 sqft, Ground + 2 floors.

1
Mon Dec 9, 2013, 8:05 pm

district CHP system

NC-2009 EAc1:Optimize energy performance
posted by  Giorgia Lorenzi  on 

I am modeling a building which is connected to a district CHP system.

1
Thu Jul 12, 2012, 6:57 pm
1
Fri Oct 22, 2010, 2:02 pm

Modeling Future Chillers

NC-2009 EAc1:Optimize energy performance
posted by  Tom Nichols  on 

We are modeling and commissioning a dormitory building where 4 pipe vertical fan coils have been installed.

1
Thu Feb 24, 2011, 12:22 pm

Comaprison of EAp2 and EAc1

NC-2009 EAc1:Optimize energy performance
posted by  BABAR MEHMOOD  on 

I want to clarify that ASHRAE 90.1 Appendix G 2007 (sec 5.4, 6.4, 7.4, 8.4, 9.4 and 10.4 ) is applicable to Option-1 Whole building energy simulation for both EA Prerequisite 2 and EA Credit 1.

1
Thu Feb 28, 2013, 3:00 pm

CHP modelling Option 1 question

NC-2009 EAc1:Optimize energy performance
posted by  Eszter Gulacsy  on 

I think I posted this question on the wrong page beforehand, so I'll post it again here. We are trying to account for a CHP plant near our project in our energy model.

1
Wed Oct 26, 2011, 6:06 pm

EAc1 points using DES Option 1 + A lot of Renewables

NC-2009 EAc1:Optimize energy performance
posted by  Reniel Barroso  on 

We have a project opting to get the maximum 19 credit points in EAc1.

1
Wed Aug 31, 2016, 3:45 pm

High Energy Testing Equipment

NC-2009 EAc1:Optimize energy performance
posted by  Joel Simonyak  on 

We are including a r&d / manufacturing space within our LEED project boundary that includes several pieces of testing equipment & support spaces which provide necessary conditions to comple

1
Mon Jul 22, 2013, 2:47 pm