No HVAC / Natural Ventilation - Unmet Hrs

NC-2009 EAp2:Minimum Energy Performance
posted by  Chad Coleman  on 

Hello, I am currently working on a LEED NCv2009 project which includes a small building ~1,150sf, and has 200sf of regularly occupied space.

10
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jul 23, 2013, 2:38 pm

Proposed ERV vs. Baseline VAV

NC-2009 EAp2:Minimum Energy Performance
posted by  Laura Long  on 

I have a question regarding G3.1.2.8. Per this section a return fan is required for the baseline system if there is a return fan in the proposed model.

3
b.i.g. Bechtold DesignBuilder Expert
LEEDuser Basic Member
581 thumbs up
Wed Jul 17, 2013, 3:04 pm

Fan power BaseLine

NC-2009 EAp2:Minimum Energy Performance
posted by  VICTOR MORENO  on 

Hello everybody, I´m simulating a LEED Project. When calculating the powers of the fans as G3.1.2.9, the result is adequate.

5
Green Building Energy Consultant
Green Living Projects
LEEDuser Basic Member
2 thumbs up
Wed Jul 17, 2013, 12:55 pm

regularly occupied sf

NC-2009 EAp2:Minimum Energy Performance
posted by  Jean Marais  on 

1) Why is column regularly occupied sf in leedonline EAp2-1 table needed? 2) We have filled out EAp2-1 as per the spaces used in the energy model, not the project per say...i.e.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Jul 15, 2013, 7:18 pm

Exterior Lighting for Baseline

NC-2009 EAp2:Minimum Energy Performance
posted by  Jatuwat Varodompun  on 

Should we use the power density of the 90.1 without addenda or should we use the addendum I for the "baseline" of the energy simulation of EAp2?

3
Sr. Electrical Engineer
Integrated Design Solutions
LEEDuser Expert
516 thumbs up
Mon Jul 15, 2013, 2:30 pm

Minimum/Mandatory Requirements for, VAV TU?

NC-2009 EAp2:Minimum Energy Performance
posted by  Jorge Torres-Coto  on 

I have a Tenant Improvement that has VAV terminal units connected to an existing VAV AHU. The contractor and owner decided to save money and utilize stand alone control.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 11, 2013, 7:58 pm

Chillers COP consideration equivalent

NC-2009 EAp2:Minimum Energy Performance
posted by  Mohd Imran Shaikh  on 

Hi There, We are looking into a project which an office building and is going to be LEED certified.

5
Thu Jul 11, 2013, 2:47 pm

Proposed v Baseline Outdoor air

NC-2009 EAp2:Minimum Energy Performance
posted by  Joseph Snider  on 

I am working on a multifamily building. The proposed system is a Rooftop unit with constant vlume and 100% outdoor air.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jul 11, 2013, 8:22 am

Unconditioned Spaces

NC-2009 EAp2:Minimum Energy Performance
posted by  Laura Long  on 

While modeling the building in the space-by-space method, there are a couple of closets that are not conditioned, therefore have been model as unconditioned in TRACE 700.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Jul 10, 2013, 6:46 pm

Task Lighting

NC-2009 EAp2:Minimum Energy Performance
posted by  Omar Elrawy  on 

I have two questions concerning Task Lighting: 1- for an office building, should I count task lighting as process load? 2- For Base-case Simulation, does the LPD limit set by ASHRAE 90.1 include