can we get credit for a future cistern?
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Saju Varghese on
If we have prepared piping but cistern is not installed yet and it will possibly be installed in the future, can we get credit for it?
Treated wastewater definition.
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Diaa Madkour on
Hi, working on an office building project, we r pursuing this credit through option 2 : "Treat 50% of wastewater on-site...etc." Through the design Preliminary Review we received a comment stating
Treated (rain) water for human contact...
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Jorge Lopez de Obeso on
Here is a situation: Rain water is captured and treated for reusing to flush and flow fixtures. A single cistern storages both rainwater and municipal water supply.
On-site waste water treatment in LEED V4
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Lorne Mlotek on
Are Lagoons, or septic tanks rewarded at all in LEED V4? This credit was omitted from the new version and I am curious if I installed an on-site waste water treatment facility onsite which dischar
WEc2: Time frame for functional reclaimed water systems
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Brian Bartholomew on
Under the Bird's Eye View here for WEc2, there is a citation of LEED Interpretation #10012 made on 05/09/2011 which states "projects may only count future infrastructure such as reclaimed water sys
Waste Water Calculation for Option 2
NC-2009 WEc2:Innovative Wastewater Technologiesposted by sompoche sirichote on
LEED template use the flush fixture water which calculated based on occupant usage.
Option 2 - CIR's
NC-2009 WEc2:Innovative Wastewater Technologiesposted by Donald Green on
Can anyone who submitted a CIR for Option 2 regarding a campus situation post your results?