How does GBCI ccalculate reclaimed water reduction?

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  David Gibney  on 

This is an academic problem that I need confirmation for. It’s a LEED-NC 2009 project. • 242 FTEs. No visitors, etc. 50:50 gender ratio = 121 of each.

1
Fri Nov 27, 2015, 7:32 pm

WE 2.2 states, "minimize the

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  David Holmes  on 

WE 2.2 states, "minimize the amount of wastewater conveyed to the municipal system" Can we automatically acheive this Credit by using an onsite Well and Septic system?

1
Thu Dec 13, 2012, 9:26 pm
1
Fri Oct 29, 2010, 9:24 pm

Does restaurant dishwashers qualify as waste water?

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Kristopher Lashley  on 

I am wondering if I can include a restaurant dishwasher in my waste water calculations for WEc2? According to the reference guide waste water is defined as "the spent or used water from a home, co

1
Fri Nov 27, 2015, 7:34 pm

0.8 gpf water closets, no urinals

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Sam Farmer  on 

We have a project that is considering a 0.8 gpf water closet. The project is an existing building renovation and we do not have ADA clearance space for the addition of urinals.

1
Sun Nov 3, 2013, 6:40 pm

Non-potable water for sewage conveyance required for option 1?

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Valentin Grimaud  on 

Dear community, We have pursued this credit with option 1 and have achieved 52.31% only with the use of high efficiency WC and urinals.

1
Thu Mar 27, 2014, 4:45 pm
1
Wed Sep 29, 2010, 3:37 am

Water Efficiency Calculation

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  ABDUL MUTHALIB MOHAMED  on 

Hi, My project is a factory building. They are installing only Indian Water Closets and no Urinals. How to calculate water efficiency if Urinals are not used?

1
Fri Nov 27, 2015, 7:36 pm

can we get credit for a future cistern?

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Saju Varghese  on 

If we have prepared piping but cistern is not installed yet and it will possibly be installed in the future, can we get credit for it?

1
Mon Nov 4, 2013, 9:55 pm

Treated wastewater definition.

NC-2009 WEc2:Innovative Wastewater Technologies
posted by  Diaa Madkour  on 

Hi, working on an office building project, we r pursuing this credit through option 2 : "Treat 50% of wastewater on-site...etc." Through the design Preliminary Review we received a comment stating

1
Thu Aug 2, 2012, 3:51 pm