Post a question or comment
Credit Filters
Construction activity pollution prevention
Filter by location
Forum
Topic
Replies
Recent

Is it too late to do SSp1?

NC-2009 SSp1:Construction activity pollution prevention
posted by  Indochine Engineering VN  on 

Hi, My project is a hotel and client just decided to do LEED when Construction of structure is almost done.

0

Vehicle tracking control dirt road

NC-2009 SSp1:Construction activity pollution prevention
posted by  Juan Robles  on 

We are working on a project in Costa Rica where the access road is a dirt road.

1
Fri Jul 12, 2013, 3:04 pm

Implementation of ESC Plan

NC-2009 SSp1:Construction activity pollution prevention
posted by  Stephen Buonopane  on 

My question is in regard to the following requirement from SS Prereq 1: "Create and implement an erosion and sedimentation control plan…" In particular I am interested in USGBC's interpretation of

1
Wed Jun 18, 2014, 2:37 pm

Mosquitos eradicate substance

NC-2009 SSp1:Construction activity pollution prevention
posted by  Tota Yun  on 

How I can know if this substance which already used by the contractor in new construction project comply with LEED DELTABAZ 25 EC

2
Founder & Community Director
Metricorps
LEEDuser Expert
7781 thumbs up
Mon Jan 9, 2017, 5:11 am

Perimeter protection

NC-2009 SSp1:Construction activity pollution prevention
posted by  Martin Meehan  on 

We have a number of LEED projects in infill locations in Ireland. Since we don't really have a standard code for site Erosion and Sedimentation we have to stick to the U.S.

3
Default Avatar
Principal
Meehan Associates
LEEDuser Basic Member
14 thumbs up
Thu Feb 11, 2016, 6:22 pm

Construction Activity and Pollution Prevention

NC-2009 SSp1:Construction activity pollution prevention
posted by  JP Rout  on 

We have Project intending to be registered under LEED 2009 BD+C for major renovations.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7781 thumbs up
Mon Jan 25, 2016, 9:13 am

ESC gap between the excavation phase and construction phase

NC-2009 SSp1:Construction activity pollution prevention
posted by  Meghan Ward  on 

I am working on a 2-building campus project where an ESC plan was implemented during excavations phase (bulk earthworks) of the whole campus.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7781 thumbs up
Mon Nov 30, 2015, 8:43 am

Vehicular control - Tire washing control

NC-2009 SSp1:Construction activity pollution prevention
posted by  LEED Pro Consultant  on 

Hello all, I have a question regarding the control measure for the control for all the vehicles leaving the project, the most common is cleaning all the vehicles (washing the tires) before leaving

4
Tue Aug 4, 2015, 10:03 pm

Reactivating construction with ESC Plan, no ESC Plan before

NC-2009 SSp1:Construction activity pollution prevention
posted by  LEED Pro Consultant  on 

Hello! We have a project that started construction some time ago, and stopped 1 yr ago, leaving only the foundation. At this time, they were not considering LEED as an objective.

4
LEED Project Manager
SIDEworks
LEEDuser Basic Member
0 thumbs up
Tue Jun 16, 2015, 10:33 pm

Sediment Basin dimensioning

NC-2009 SSp1:Construction activity pollution prevention
posted by  Paula Hernandez  on 

Hi, this may be a silly question. When dimensioning a temporary sediment basin, the CGP says to use either the calculations for the 24 hs- 2 year desing storm or 3600 cubic feet x acre drained.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Wed Apr 8, 2015, 8:22 pm