Is it too late to do SSp1?
NC-2009 SSp1:Construction activity pollution preventionposted by Indochine Engineering VN on
Hi, My project is a hotel and client just decided to do LEED when Construction of structure is almost done.
Vehicle tracking control dirt road
NC-2009 SSp1:Construction activity pollution preventionposted by Juan Robles on
We are working on a project in Costa Rica where the access road is a dirt road.
Implementation of ESC Plan
NC-2009 SSp1:Construction activity pollution preventionposted by Stephen Buonopane on
My question is in regard to the following requirement from SS Prereq 1: "Create and implement an erosion and sedimentation control plan…" In particular I am interested in USGBC's interpretation of
Mosquitos eradicate substance
NC-2009 SSp1:Construction activity pollution preventionposted by Tota Yun on
How I can know if this substance which already used by the contractor in new construction project comply with LEED DELTABAZ 25 EC
Perimeter protection
NC-2009 SSp1:Construction activity pollution preventionposted by Martin Meehan on
We have a number of LEED projects in infill locations in Ireland. Since we don't really have a standard code for site Erosion and Sedimentation we have to stick to the U.S.
Construction Activity and Pollution Prevention
NC-2009 SSp1:Construction activity pollution preventionposted by JP Rout on
We have Project intending to be registered under LEED 2009 BD+C for major renovations.
ESC gap between the excavation phase and construction phase
NC-2009 SSp1:Construction activity pollution preventionposted by Meghan Ward on
I am working on a 2-building campus project where an ESC plan was implemented during excavations phase (bulk earthworks) of the whole campus.
Vehicular control - Tire washing control
NC-2009 SSp1:Construction activity pollution preventionposted by LEED Pro Consultant on
Hello all, I have a question regarding the control measure for the control for all the vehicles leaving the project, the most common is cleaning all the vehicles (washing the tires) before leaving
Reactivating construction with ESC Plan, no ESC Plan before
NC-2009 SSp1:Construction activity pollution preventionposted by LEED Pro Consultant on
Hello! We have a project that started construction some time ago, and stopped 1 yr ago, leaving only the foundation. At this time, they were not considering LEED as an objective.
Sediment Basin dimensioning
NC-2009 SSp1:Construction activity pollution preventionposted by Paula Hernandez on
Hi, this may be a silly question. When dimensioning a temporary sediment basin, the CGP says to use either the calculations for the 24 hs- 2 year desing storm or 3600 cubic feet x acre drained.