Hi, this may be a silly question. When dimensioning a temporary sediment basin, the CGP says to use either the calculations for the 24 hs- 2 year desing storm or 3600 cubic feet x acre drained. If using the 24hs-2year desing storm, we should be using the figures for the post-development situation, not the pre-development situation, am I right? Particularly when the site more than 50% pervious in the pre-development situation. Sorry, but this is not common practice here. Thanks!