NC-2009 PIf1:Minimum Program Requirementsposted by Stella Stella on
Hi, we are currently working on a project which is nearing substantial completion but we haven't yet done our design submissions for LEED. will it affect our LEED certification? please advice.
One or two separate buildings
NC-2009 PIf1:Minimum Program Requirementsposted by Felipe Holguin on
I have a project with two buildings that are attached physically by two underground levels with services as parking spaces, bicycle racks, showers and bathrooms and MEP systems shared for both bu
Site
NC-2009 PIf1:Minimum Program Requirementsposted by K Nakamura on
We have a project- scope is 2 new buildings, no sitework/landscape.
Office Transient
NC-2009 PIf1:Minimum Program Requirementsposted by Nate Steeber on
I received some technical advice on my project regarding the occupancy. I have a mixed-use building. Primarily office spaces with a tenant fit out cafe and restaurant.
Multiple Buildings but Really One Project
NC-2009 PIf1:Minimum Program Requirementsposted by Erica Timmons on
We are working on a university campus.
Incomplete Spaces
NC-2009 PIf1:Minimum Program Requirementsposted by Annalise Reichert on
I know that if there are incomplete spaces at the time of certification the owner needs to write a letter of commitment indicating the remaining spaces will satisfy LEED requirements.
Submittal templates in metric Units
NC-2009 PIf1:Minimum Program Requirementsposted by BABAR MEHMOOD on
We have a project in KSA and want to fill the online submittal templates regarding the Health care but we found the Imperial system for the templates, whereas metric system is follwed for all LEED
Future-Fit Out Spaces LEED Certified or Not
NC-2009 PIf1:Minimum Program Requirementsposted by Catherine Blakemore on
My inquiry is in reference to CIR 10102 I have healthcare project that is a surgical addition at a local hospital. The 2nd floor of this addition is a future fit-out space to be determined.
About MPR#6 in PIf1
NC-2009 PIf1:Minimum Program Requirementsposted by Ron Dean on
Hello, I have a question about filling PIf1 out in leedonline, this is about complying with all the MPRs. Our building will use energy and water meters to report our data to USGBC.
ENERGY STAR sharing data in NC-2009
NC-2009 PIf1:Minimum Program Requirementsposted by Ryan L on
For our project we have selected Option 1: Energy and Water Data Release Form.