Is there still an exemplary performance point available if you double the required thresholds?
CI-v4 MRc3:Building product disclosure and optimization - environmental product declarationsposted by Landry Watson on
Can anyone confirm if there is still an exemplary performance point available for Options 1/2 if you double the performance thresholds even now that they dropped the original thresholds to half of
Inpatient Visitors using Inpatient Restrooms - How to Calculate
Healthcare-v4 WEp2:Indoor water use reductionposted by Heather Ane Zeto on
I may be overthinking this - but hopeful someone can chime in with project/review experience! We are working on a new hospital. I understand that the LEED Reference Guide clearly states
VOC content requirement for adhesives and sealants
CI-v4 EQc2:Low emitting materialsposted by Nadia Azzam on
What are acceptable forms of documentation that satisfy the VOC content evaluation requirement for adhesives and sealants?
Meter on Domestic hot water vs. Cold-water makeup for domestic hot water systems
Healthcare-v4 WEc4:Water meteringposted by Mark Benson on
Can someone explain the difference between a meter measuring domestic hot water consumption and a meter measuring cold-water makeup for domestic hot water systems? The first meter can be used
Meters on closed-loop hydronic system makeup water
Healthcare-v4 WEc4:Water meteringposted by Mark Benson on
Many healthcare projects have closed-loop hydronic systems for chilled water and heating hot water. Would providing separate meters for chilled water make-up and hot water make-up count as tw
Separate measurement of cold and hot lines for healthcare water uses
Healthcare-v4 WEc4:Water meteringposted by Mark Benson on
For healthcare projects, projects must "install water meters in any five" water uses listed. However, many of these water uses, such as dietary, laundry, laboratory, etc.
upload daylight calculation of seperate building in a Group for a Master Site
Warehouses-NC-v4 EQc7:Daylightposted by N. Josef Nassif on
Dear Community
I hope you are doing fine.
Furniture reuse
CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materialsposted by Marie Miller on
Hello - I'm working on a TI project and the client is reusing over half their furniture. I know I include this in the calculator, but do I use the value of the furniture when it was purchased?
Adjustable luminaries tilt - Option 1 (BUG) Vs Option 2 (Calculation)
NC-v4 SSc6:Light pollution reductionposted by Anna Korinkova on
Hi,
I would like to clarify how to characterize adjustable luminaires.
Pilot Credit: Procurement of Low Carbon Construction Materials (Cemco Sure-Board)
NC-v4 INc1:Innovationposted by Dejana Harris on
A project pursuing MRpc123 Procurement of Low Carbon Construction Materials is using Cemco Sure-Board, which is a prefabricated fiber cement panel and steel assembly.