Pilot Closed - attending LEED v4.1 Optimize Process Water Use

Pilot-Credits WEpc94:No Cooling Tower
posted by  Adriana Hansen  on 

This pilot credit has been used in many office projects with VRF system and at least one of the baseline system(s) designated for the building using ASHRAE 90.1-2010 Appendix G Table G3.1.1 in

0

Pilot Closed - attending LEED v4.1 Optimize Process Water Use

Pilot-Credits WEpc94:No Cooling Tower
posted by  Adriana Hansen  on 

This pilot credit allows to many office buildings that have a VRF system and at least one of the baseline system(s) designated for the building using ASHRAE 90.1-2010 Appendix G Table G3.1.1 includ

0

No Cooling Tower ACP Feedback

Pilot-Credits WEpc94:No Cooling Tower
posted by     on 

I found this pilot credit to be a great way to allow projects to earn credit for the design choice of choosing not to utilize cooling towers on the project even for buildings that are lar

1
Tue Jun 11, 2024, 10:45 pm

NC Building with no cooling tower

Pilot-Credits WEpc94:No Cooling Tower
posted by  Paula Hernandez  on 

Hi, I think that this is a very helpfull credit for all the buildings that does not have a cooling tower in their HVAC systems.

0

Documentation for No Cooling Tower

Pilot-Credits WEpc94:No Cooling Tower
posted by  Marelle Davey  on 

Hi everyone,

Just wondering what documentation have folks used to achieve this credit? Is any documentation required besides mechanical drawings? 

Thanks!

2
Sustainability Consultant
WSP
LEEDuser Expert
0 thumbs up
Tue Mar 14, 2023, 8:20 am

No Cooling Tower Sweden

Pilot-Credits WEpc94:No Cooling Tower
posted by  Louise Holmstedt  on 

We are pursuing this pilot credit as ACP for a Swedish Project. We Think it is fair that Projects without cooling Towers can achieve the no cooling Tower credit too.

0

Cooling Towers to meet the loads of uninterrupted office systems

Pilot-Credits WEpc94:No Cooling Tower
posted by  Adriana Hansen  on 

Could projects with HVAC system base conception composed by direct expansion air cooled VRF system for all spaces, but including a condensing water plant to provide a condensate water point to

0

Pilot-Credits WEpc94

Pilot-Credits WEpc94:No Cooling Tower
posted by  Nermin Hegazy  on 

 

I have a question regarding one of the conditions to be met to achieve this credit:

1
Wed Nov 30, 2022, 2:50 pm

ACP for No Cooling Tower

Pilot-Credits WEpc94:No Cooling Tower
posted by  Natalie Terrill  on 

This is a straight forward, easy to document credit for projects that can demonstrate compliance.

7
Senior PM, Sustainability Consultant
Re:Vision Architecture
LEEDuser Basic Member
28 thumbs up
Thu Aug 18, 2022, 5:50 pm

Evaporative Cooling Fan is not available to meet No Cooling Tower option?

Pilot-Credits WEpc94:No Cooling Tower
posted by  Esteban Martinez  on 

We are working on a project without Cooling Tower, also the HVAC system has an Evaporative Cooling Fan.

Does this make that the project can not pursue this credit? 

0