EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Sofia Barahona on
We are currently carrying out the feasibility study for the certification of an existing project in Operation and Maintenance v4.1: Existing Buildings.
Two unidentical buildings from same owner/management for what approach?
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Eric Bautista on
I would like to emphasize the general details of this project for LEED v4 or v4.1 O+M certification.
MRp2 & SSc2
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Laura Danzig on
Hi there.
I have a question regarding identifying the LEED project boundary as it relates to rainwater management.
One Address but buildings are not physically Attached
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Jay Murray on
The owner of an office property wants to go for LEED EBOM. There are 3 buildings, two are attached with an architectural overhang and the third is roughly 40 feet away.
Building Eligibility + Project Boundary
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Julia Perez on
Hi I have a bit of a particular project here, let me explain. We want to certify 5 office buildings under LEED v4 EBOM.
Can a LEED NC certified building pursue now a LEED EBOM?
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Veronica Reed on
Hello, our project, an airport terminal, got LEED Gold certified this month under version 2.2. The owner now wants to explore certifying the building for operations and maintenance under V4.
2 office floors on a 20 stories building
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Michael E. Edmonds-Bauer on
Hello, We have a cliente that is interested in pursuing LEED for his brand new offices.
What is an "Existing Buiding" for EB:OM?
EBOM-v4 MPR2:Must use reasonable LEED boundariesposted by Davide Filippi on
An existing, old and close building (nobody insiede for years, no heating system working...) can pursue a LEED EB:OM v4 Existing building?