Recycling Building Products

CS-v4 MRc5:Construction and demolition waste management
posted by  Ciaran McCabe  on 
Hi, if existing building materials, such as concrete as an example, is removed from site during demolition, is there benefits if this was processed offsite and reused in there of gravel for the same
2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Apr 23, 2024, 3:47 pm

LEED v4 Waste Monitoring unit of measurement in Truck Load

CS-v4 MRc5:Construction and demolition waste management
posted by  Ronnel Flores  on 

Our project's waste quantity was recorded in truck load not in kilograms. This counts as volume?

4
Managing Partner
Innovative Workshop Consulting
LEEDuser Expert
22 thumbs up
Thu Jul 20, 2023, 3:19 pm

On site or Off site seperation

CS-v4 MRc5:Construction and demolition waste management
posted by  Andrea Tirao  on 

Our project has extensive generation of wastes into different activity zones.

0

Recycling rate of construction and demolition waste

CS-v4 MRc5:Construction and demolition waste management
posted by  Tiago Rigobello  on 

How can we prove the recycling rate of construction and demolition waste made by the recycler? What are the options in Brazil?

 

Thanks! Best regards!

0

Comingled waste on site - separation at waste facility

CS-v4 MRc5:Construction and demolition waste management
posted by  Alicia Ravetto  on 

Is this always considered a single stream? What method of documentation should the waste facility provide to comply with the requirement of this credit?

4
CPC, LEED AP BD+C
Durotech, Inc.
LEEDuser Basic Member
3 thumbs up
Thu Oct 3, 2019, 9:31 pm

Volume to Weight Conversion for LEED v4

CS-v4 MRc5:Construction and demolition waste management
posted by  Estra Marku  on 

LEED v2009 allowed us to use the volume to weight conversion methodology to track our projects waste.

1
Thu Jul 18, 2019, 7:22 pm

Construction Waste Management Core and Shell and Tenant Upfit Spaces

CS-v4 MRc5:Construction and demolition waste management
posted by  Summer Minchew  on 

Can a Core and Shell project include tenant construction debris in overall CWM calculations? Often tenant construction is concurrent with core and shell construction.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Feb 26, 2019, 6:22 am

Brick and rubble in soil

CS-v4 MRc5:Construction and demolition waste management
posted by  Marilyn Specht  on 

We are working on a LEED v4 Core & Shell project in an urban core. We are targeting 2 points for MRc5 and have an aggressive Construction & Demolition Waste Management Plan underway.

2
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Mon Mar 12, 2018, 5:59 pm