Confusion over adjacency and shared systems

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  GBD Architects  on 

Hi all, We are looking to certify a new childcare building on a higher-ed campus that will be sharing HVAC systems with an existing childcare building.

4
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Sat Feb 4, 2017, 4:07 am

LEED Boundary and Complete Building Question...

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Roxanne Button  on 

This may be more in line with MPR #1, but it also has to do with the LEED boundary so I'll post it here first.

6
Architect & Sustainable Design Consultant, AIA, MRAIC, LEED AP
Design Synergies Architecture
LEEDuser Basic Member
49 thumbs up
Mon Jan 23, 2017, 5:50 pm

URGENT - Eligibility Advice needed right away!

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Erica Downs  on 

If anyone can, I need an answer ASAP -- The project will be a new-construction Concrete Manufacturing Plant.

3
Default Avatar
LEED Consultant
The Green Engineer
LEEDuser Basic Member
188 thumbs up
Fri Jan 13, 2017, 7:28 pm

Project Boundary

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Sharon Dearstyne  on 

We have a 11 story Historical hotel with 6 floors of Guest Rooms that are being completely renovated. The remaining floors are Ballrooms, meeting spaces and retail.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu May 26, 2016, 6:30 pm