Sum of LPBs = 100% of LCB?
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Zonda E. Team on
Dear all, I find these below in contradiction. If so, does anybody know which is correct? Supplemental Guidance to MPR revision 2 (1 Sep 2011) - MPR 3: "3.
Non-contiguous land to associate with LEED boundary
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Julie Blue on
To support this project we installed a geo-thermal system under an existing playing field that is across the street from the new building addition we are certifying.
Site boundary for a project mixing Leed & non Leed new buildings
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by serge sidoroff on
Is it possible to submit to the Leed certification only one of two adjacent new buildings, an office building and an industrial plant ?
LEED project boundary in underground garage
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Michael Haugeneder on
Hello everyone, we're facing a complex situation with regard to the determination of our LEED project boundary.
project boundary definition
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Emmanuel Pauwels on
Our Project consists of land that is property of the owner.
Certifying one LEED building on a campus
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Lisa Sawin on
We have currently drawn our LEED boundary to include all areas that our building/scope of work is impacting.
what can be included in LEED project boundary?
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Adam Targowski on
The owner has a land which is divided into 3 parts.
Campus Projects Boundaries and LED sitelights w/ OC
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Saju Varghese on
We are currently having a campus containing 11 buildings/structures out of which, 6 are going to be LEED certified.
Subway stations
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Valentin Grimaud on
Hello everyone, we are looking at the feasibility of doing LEED for subway stations.
Interior Renovations and Non-Contiguous Parcels as Part of LPB
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Brooks Critchfield on
We have a very large existing facility registered under LEED-CI which will be partially renovated and partially updated.