IAQ testing

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Danielle Dunn  on 

"One test is required for each separate ventilation system within the building, with not less than one sample per 25,000 ft2 of contiguous floor area."

 

0

2 options, Flush out and Air testing

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Yazmin Trueba  on 

230k School, Tight Schedule, Path 1 Flushout before occupancy, Per Phases, 21 Air Handler Units / Zones, 6 areas of Flushout durations from 99 days to 30 days. My questions: 1.

1
Tue Nov 5, 2013, 1:33 am

Monitoring Humidity?

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Ara Massey  on 

I am currently working on a project in southern Colorado (very dry) that is doing a phased flush-out but there is currently no way to monitor interior humidity.

1
Thu Nov 17, 2011, 4:30 am

Flush out and un-touched area in LEED boundary

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Todd Bundren  on 

My project includes the renovation of an existing building and a major attached addition (over 70% of the project is new construction).

1
Tue Nov 5, 2013, 1:34 am

IAQ Testing and Furnishings

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Q +  on 

The Credit Language contains this statement regarding air quality testing and furnishings: "Movable furnishings such as workstations and partitions should be in place for the testing, although it

1
Tue Mar 29, 2011, 4:38 am

Phased IAQ Testing?

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Q +  on 

Is it acceptable to perform air quality testing in phases? The project in question is a 175K sf school designed in 7 zones.

1
Tue Mar 29, 2011, 4:36 am

measuring and reporting temperature & RH

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Eri Spaulding  on 

Does anybody know how to measure and report indoor temperatures and relative humidity during flushout? Do we need to record min. and max. every single day at every single room?

1
Wed May 2, 2012, 8:25 pm

Flush Out in Stages

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Nell Achtmeyer  on 

I am wondering if it's possible to sequence the flush out in stages so that you can make your way through the building, but also maintain work in other parts as well...

1
Fri Mar 16, 2012, 4:58 pm

Post construction AND Post Occupancy Flush Out

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Denise Domino  on 

3.2 IAQ Mgmt. Plan - What are your options if neither Option 1 or 2 were done?

1
Sun Aug 27, 2017, 12:09 am

IAQ Management Plan - Post construction measures

Schools-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Maya Karkour  on 

Dear all, The LEEDOnline letter template for IEQc3.2 includes a portal to upload the IAQ Management Plan highlighting post-construction IAQ management practices. Is this plan different from the o

4
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Jul 13, 2017, 1:45 pm