Is it acceptable to perform air quality testing in phases? The project in question is a 175K sf school designed in 7 zones. We would like to begin testing on half of these zones while test and balance, etc. is still going on in the others. Is this acceptable as long as all items required to be complete prior to testing are complete in the zones being tested?