CS-2009 MRc5:Regional Materials
posted by  Michael E. Edmonds-Bauer  on 

I would like to know how we must prove GBCI about materials cost. We are requesting our contractor to provide the following for steel rebars: 1.

1
Fri Mar 22, 2013, 4:38 am

MR5

CS-2009 MRc5:Regional Materials
posted by  Christine Castellano  on 

Steel sub listed 76.60% of raw materials extracted within 500 miles of project, the data he provided for back-up lists 5 different locations where the raw material was extracted but manufacturer ca

1
Wed Jun 18, 2014, 4:52 pm

Core and Shell Scope & Tenant Scope

CS-2009 MRc5:Regional Materials
posted by  Osama Hassan  on 

Hi, Project is registered on Core & Shell rating System CS V2.0. When i was working on Regional Material Credit MRc5, I found two Options.

0

Does water count for MRc4 and MRc5

CS-2009 MRc5:Regional Materials
posted by  Anna Korinkova  on 

Does water as a part e.g.

1
Tue Dec 18, 2012, 9:53 pm

MR5

CS-2009 MRc5:Regional Materials
posted by  Christine Castellano  on 

accidentally posted this in MR4 - "this is my first time inputting into LeedOnline - as I cannot find interactive help on that site - I have no idea what to put in the columns where the extraction

1
Tue Jun 17, 2014, 9:02 pm

BDC Material & Resource Calculator- Percentage Regional

CS-2009 MRc5:Regional Materials
posted by  Suha Hyderabad  on 

I have a question regarding the BDC Material Tracker, % Regional.

2
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Sun Jan 25, 2015, 8:07 pm

LEED Letter template

CS-2009 MRc5:Regional Materials
posted by  Steve Salzman  on 

I am looking for the LEED letter template for CS 2.0 MRc5 (the credit requirements specify that this is necessary in order to capture the credit for the tenant lease/sales option).

3
Default Avatar
Project Engineer, LEED AP
SRC, Inc
LEEDuser Basic Member
0 thumbs up
Sun Jan 25, 2015, 7:21 pm

Different sources

CS-2009 MRc5:Regional Materials
posted by  Mike D  on 

On one project we are working on, the manufactuer sources iron ore from many countries and he is unable to say what ore was used in any particular batch of steel. How do we determine this?

3
Default Avatar
Principal
LSDesignworks @ Vancouver, BC Canada
LEEDuser Basic Member
9 thumbs up
Tue Jun 17, 2014, 8:40 pm

Length of supply chain

CS-2009 MRc5:Regional Materials
posted by  Magnus Stagnäs  on 

Sometimes the supply chain from the extraction of virgin material to the complete assembly may be very long and difficult to document.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Mon Jun 16, 2014, 5:23 pm