Baseline System for Warehouse Shell

CS-2009 EAp2:Minimum Energy Performance
posted by  Tony Schafer  on 

Wondering how to determine the baseline system for a warehouse that upon initial completion will be a cold, dark shell maintained at 50°F.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Aug 15, 2012, 5:31 pm

High Hazard Areas for Core & Shell

CS-2009 EAp2:Minimum Energy Performance
posted by  Michael Trzcinski  on 

We are working on a warehouse building with attached offices in climate zone 5A, with gas-fired rooftop equipment for heating.

3
Default Avatar
Project Engineer
Hesnor Engineering Associates, PLLC
LEEDuser Basic Member
5 thumbs up
Tue Aug 14, 2012, 9:52 pm

Natural Ventilation

CS-2009 EAp2:Minimum Energy Performance
posted by  Luana Bertoletti  on 

Hi! Currently, I'm working on a warehouse's project under LEED certification. There's no heating/cooling system in the warehouses, there's only natural ventilation.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Aug 14, 2012, 1:02 pm

ASHRAE 90.1 Exit signs - Mandatory Provisions

CS-2009 EAp2:Minimum Energy Performance
posted by  Bernadette Stauder-Buschlinger  on 

In the CS- project the exit signs are considered to be a part of the emergency lighting. Therefore the lamps are off during normal operation. The proposed exit sign exceed 5 W per face.

8
Bilfinger Baugesellschaft m.b.H.
LEEDuser Basic Member
2 thumbs up
Sat Jul 28, 2012, 7:03 am

Ashrae 90.1

CS-2009 EAp2:Minimum Energy Performance
posted by  Ron Dean  on 

Hello, I am wonderinq if you can help me: where no heating system exists the heating system classification shall be asummed to be electric, and the system characteristics shall be identical to the

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Tue Jun 26, 2012, 8:42 pm

Identical fan power?

CS-2009 EAp2:Minimum Energy Performance
posted by  Laura Howe  on 

We have a comment back from GBCI, stating: 1. The Baseline fan power calculations and the SV-A reports for the Baseline model indicate that the exhaust fan systems (xxx1 and xxx2, as indicated in

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jun 26, 2012, 8:06 pm

Process Load for CS

CS-2009 EAp2:Minimum Energy Performance
posted by  Yu Wang  on 

Hallo everyone, I have a question about process energy. My project is a mixed use for CS, contains office, laboratory, lobby, storage and corridor.

5
Mechanical Engineer
SCHOLZE Consulting GmbH
LEEDuser Basic Member
10 thumbs up
Fri Jun 15, 2012, 1:18 pm

C&S project

CS-2009 EAp2:Minimum Energy Performance
posted by  Ron Dean  on 

Hello, i am modeling a C&S project- building of 22 floors. clime type:2A .

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Thu Jun 7, 2012, 2:59 pm

Building Area Method applicable for Multi-use-building

CS-2009 EAp2:Minimum Energy Performance
posted by  Marco Abdallah  on 

Assuming a 10 storey building where the first three floors are retail floors and the remaining 7 floors are office floors, is it generally possible to use the building area method? Is it possible t

5
Mon Jun 4, 2012, 1:06 pm

O1:Interior Lighting Power Density part of Mandatory Provisions?

CS-2009 EAp2:Minimum Energy Performance
posted by  Marco Abdallah  on 

We are pursueing OPTION 1 (Whole Building Simulation). Thus we also have to comply to the mandatory provisions, e.g. section 9.4 for lighting.