Temperature and Humidity Monitoring During Flush
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Nancy Henderson on
Is it part of the requirement of this credit to monitor temperature and humidity in the space during the flush out - or is it sufficient to provide the temperature set points and calculate the resu
Question on Selecting IAQ Test Locations
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Melissa Wrolstad on
I am working on a small ~6,500 sq. ft. LEED-CI office space.
IEQc3.2 VOC Testing
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by mark morehouse on
I have a 191,000 sf nc school that will require 11 sample points.
Option 1: Full Flush-out Before Occupancy - Is there a Min. CF?
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Michelle Bracewell-Musson on
With Option 1, Path 1, we are expected to flush-out 14,000 cf/sf of outdoor air at 60 degrees temp. and 60% humidity min. Is there a minimum ventilation rate as with Path 2 which is 0.30 cf/min.?
Is flush out possible in countries with high humidity?
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Katherine Ann Resurreccion on
Hi, we would like to know if flush out is practicable in areas where high humidity is experienced whole year, say 70-85%. Should we cancel out option 1 already and go for option 2 (IAQ testing)?
IAQ Testing AFTER Occupancy?
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by buddy pribish on
I am aware of the verbiage in the LEED reference guide for IAQ testing to be completed PRIOR to occupancy, but considering that the flushout method can be completed DURING occupancy, I was wonderin
IAQ testing in a continuously occupied office
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Maggie Edelstein on
Our project is a government office that will be continuously occupied throughout the duration of construction.
Option 1 - Path 2
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Nancy Henderson on
I just had a mechanical engineer point out that the partial flush-out option does not include the requirement to maintain 60 degree temperature and 60% humidity.
outdoor delivery rates in a naturally ventilated space
CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Vera Voropaeva on
After receiving the project's review we are asked to provide outdoor delivery rates.