I am aware of the verbiage in the LEED reference guide for IAQ testing to be completed PRIOR to occupancy, but considering that the flushout method can be completed DURING occupancy, I was wondering if anyone knows of an exception to this requirement.
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dylan Connelly
Mechanical EngineerIntegral Group
LEEDuser Expert
472 thumbs up
September 14, 2012 - 7:16 pm
No exceptions. Reviews have been consistent on this issue.