Schedule for Lighting, Occupancy, & Plug LoadsNC-v4 EAp2: Minimum Energy Performanceposted by junaid naseer on Feb 20, 2018, 12:36 am
We are working on a Hospital Project outside USA and we are going though option 1 i.e. whole building energy simulation. We do not have operational hours for the project except that it is... Last reply: Marcus Sheffer, Feb 20, 2018, 10:56 am |
|
Public use vs Building occupant useCS-2009 SSc4.4: Alternative transportation - parking capacityposted by Dina Ammar on Sep 20, 2014, 12:03 pm
In a C&S office building, the owner has provided just enough parking spaces in the basement to the building tenants to meet the local zoning minimum requirements. Those parking spaces will be... Last reply: Steve Loppnow, Dec 2, 2015, 6:51 pm |
|
Decorative LightingCI-2009 EAp2: Minimum Energy Performanceposted by Yaser Al Sharif on Aug 4, 2015, 4:22 am
Dear All, I have three questions: - We are applying for a commercial interior project, we received our final review (after prem. review) I received a new comment that wasn't... Last reply: Marcus Sheffer, Aug 4, 2015, 9:24 am |
|
Heat Recovery Counts?CS-2009 EAc2: On-Site Renewable Energyposted by Dina Ammar on Jul 28, 2015, 10:29 am
Hello, Will the energy harvested from a heat recovery equipment installed on a chiller and/or the fresh air system in our project count towards on-site... Last reply: Marcus Sheffer, Jul 28, 2015, 10:40 am |
|
Stormwater Management PlanNC-2009 SSc6.2: Stormwater design - quality controlposted by Nisreen Alhussein on Jul 10, 2015, 8:11 am
I cant find clear cut for Stormwater Management Plan definition, i mean is it using both structural and non structural plans to achieve stormwater quality control? Last reply: Michael DeVuono, Jul 10, 2015, 8:29 am |
|
Exhaust fan for chemical storageCI-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by Yaser Al Sharif on Apr 13, 2015, 8:03 am
If We have chemical storage room with 69.4 ft square in Area in our building , i want to install one exhaust fan for this room to acheive credit requirements , how can i calculate minimum... Last reply: Michelle Halle Stern, Apr 13, 2015, 10:58 am |
|
Pressure loss calculationCI-2009 EAc1.3: Optimize energy performance - HVACposted by Yaser Al Sharif on Apr 8, 2015, 9:15 am
We are registed for commercial interior rating system , the system installed in our project is vrv system, in order to comply with optimize energy performance EAC1.3 , critical path supply duct... Last reply: Marcus Sheffer, Apr 9, 2015, 11:41 am |