Too late for SSp1?

NC-v4 SSp1: Construction Activity Pollution Prevention
posted by André Harms on Jan 22, 2019, 5:00 am

Hello colleagues, I was hoping that someone might be able to provide us with some insight and guidance on how to handle this issue. Log in or register to post comments 0 Vote up! André, see the FAQ on this page which closely relates. Every situation is unique, but I have heard of plenty of situations where a proper ESC plan was not in place until some point in the project. Document what you've done and how it has met best practices as much as possible, and put an ESC plan in place going forward. You can see examples of this situation in the LEED 2009 forum for this prereq. I haven't heard...

Last reply: Tristan Roberts, Feb 6, 2019, 8:50 am

Applying MRp2 retrospectively

NC-v4 MRp2: Construction and demolition waste management planning
posted by André Harms on Jan 22, 2019, 5:07 am

A potential LEED project in Addis Ababa, Ethiopia, had already begun demolition and some construction activities before a LEED AP was appointed. The extent of the work thus far has been land...

Last reply: Tiffany Beffel, Jan 22, 2019, 3:00 pm