posted by André Harms on Jan 22, 2019, 5:00 am

and how it has met best practices as much as possible, and put an ESC plan in place going forward. You can see examples of this situation in the LEED 2009 forum for this prereq. I haven't heard...

Last reply: Tristan Roberts, Feb 6, 2019, 8:50 am

Applying MRp2 retrospectively

NC-v4 MRp2: Construction and demolition waste management planning
posted by André Harms on Jan 22, 2019, 5:07 am

A potential LEED project in Addis Ababa, Ethiopia, had already begun demolition and some construction activities before a LEED AP was appointed. The extent of the work thus far has been land...