Zone Secondary Recirculation FractionNC-v4 EQp1: Minimum indoor air quality performanceposted by Dave Hubka on Jun 19, 2023, 9:53 am
ASHRAE 62.1, Section A1.2.2 states: Er is less than 1.0 for plenum return systems with secondary recirculation (e.g. fan-powered... |
|
Creating Baseline ΗVΑC system selection based on ΑSHRAE 90.1-2010- Does Ground Floor count as….NC-v4 EAc2: Optimize Energy Performanceposted by Konstantina Kalliakoudi on Jun 16, 2023, 4:38 am
Hello to all LEED Users, Ιn our project the Building (nonresidential – 8.000 m2) consists of following levels:
Last reply: Konstantina Kalliakoudi, Jun 16, 2023, 12:27 pm |
|
Bioretention Area CalculationNC-v4 SSc4: Rainwater managementposted by on Sep 6, 2016, 5:57 pmwill be that I went to school for a long time to learn how to do this, and it isn't something you're going to learn in a forum post. You can try to follow along with that Direct Determination Method,... Last reply: Marc-André Cloutier, Jun 15, 2023, 6:42 pm |
|
Baseline System for Data centerNC-v4 EAp2: Minimum Energy Performanceposted by Rajat Wadhwa on Jun 1, 2023, 7:07 pm
Hi All, I have read som many answers regarding the baseline system for Data centers, Some are saying use system 8 some are saying use system 3 and 4, which one is the right system? I am working... Last reply: Marcus Sheffer, Jun 15, 2023, 12:39 pm |
|
Mobile Dumpster Compacting- Smash My TrashNC-v4.1 MRp2: Construction and demolition waste managementposted by William Truszkowski on Jun 14, 2023, 12:44 pm
There are a number of mobile dumpster compacting companies such as Smash My Trash or Crushr that provide dumpster compacting to roll-off 20-40 yard dumpsters. I have seen studies that mobile... |
|
If the site is walking distance from two separate stops but service the same routes can you count bothNC-v4 LTc5: Access to quality transitposted by David O'Connell on Jun 14, 2023, 7:22 am
The site is close to two different stops alexion and BDC but the two stops are serviced by the same routes ? can you count both stops towards the total number of buses i.e. if the 236 goes... |
|
LPD of Building Area MethodNC-2009 EAp2: Minimum Energy Performanceposted by Jatuwat Varodompun on Aug 18, 2016, 7:58 am
1. If we decides to use 'Building area method' for energy modeling. We have to building area type including office and parking garage. Office baseline model... Last reply: Marcus Sheffer, Jun 15, 2023, 8:35 am |
|
Roads with 40 Km / h without bicycle paths or trails are considered as bicycle network?NC-v4.1 LTc6: Bicycle facilitiesposted by Sara BENLOUBA on Feb 19, 2021, 8:15 am
We have a project located in an area where the... Last reply: David O'Connell, Jun 15, 2023, 8:09 am |
|
No more than 25% of the building’s cool-wall area facing away from the equatorPilot-Credits SSpc154: Heat Island Mitigation with Cool Wallsposted by Aleksandra Prawda on Oct 8, 2021, 7:22 am
Hi all, I was considering this pilot credit for some projects, however, I have doubts about this part of the requirement: "To avoid disproportionate placement of cool-wall materials on the... Last reply: Zeynep Cakir, Jun 15, 2023, 7:09 am |
|
"No cooling tower" option removedNC-v4.1 WEc3: Optimize Process Water Useposted by Paula Melton on Dec 2, 2020, 9:39 am
It appears that Option 2, "No Cooling Tower," has been removed from this credit with addendum #10002465. Last reply: Azra, Jun 14, 2023, 6:24 am |