Time Set Point Not Met Tolerance- Radiant Floor Heating System

NC-2009 EAp2: Minimum Energy Performance
posted by Jean Marais on Sep 29, 2010, 2:25 am

Time Set Point Not Met Tolerance is 0.2°C ( ... DOE had specified a tolerance of +-0.5F for this...energyplus has a default of 0.2 degC). Am I justified in relaxing this tolerance on a system...

Last reply: Michael Tillou, Sep 30, 2010, 10:24 am

Special Circumstances

Living with LEED Online - quirks, bugs and hiccups
posted by Cara Mae Cirignano on Sep 30, 2010, 10:22 am

Hi Jean -
Information in the special circumstances section is never required - so it shouldn't affect whether or not Y appears. If you check the 'special circumstances' box, however, the...

WEp1 LEED Online form

General forums
posted by Tristan Roberts on Sep 29, 2010, 10:52 pm

In the WEp1 form, the Pl3 numbers are shown, but then you can enter your own numbers that may reflect more specific project conditions, like yours.
The following note appears in the LEED...

demonstrating compliance

General forums
posted by Tristan Roberts on Sep 29, 2010, 10:41 pm

I would agree that you can demonstrate compliance with those credits for just the one occupied space.

LEED LCA Calculator Questions and Observations

Pilot-Credits PC1: Life-Cycle Assessment (LCA) of Building Assemblies and Materials 
posted by Dirk Kestner on Sep 23, 2010, 6:47 pm

I just finished importing my data from the EC into the online LEED LCA Credit calculator and have a few questions and observations that might be helpful for others pursuing the credit.

Q1...

Last reply: Whit Faulconer, Sep 29, 2010, 12:43 pm

100% WATER CONSUMPTION FROM TREATED HARVESTED RAIN WATER

EBOM-2009 WEc2: Additional Indoor Plumbing Fixture and Fitting Efficiency
posted by Yong Lee Low on Jul 27, 2010, 6:24 am

The project I am working on is using 100% of its water demand by collecting rain water in a man made lake in its boundary and then treating it in a water treatment facility,also in its site.Does...

Last reply: Tristan Roberts, Sep 29, 2010, 12:32 pm

dual flush calculation

NC-2009 WEc2: Innovative Wastewater Technologies
posted by Jim Park on Sep 14, 2010, 9:41 pm

total daily uses # of...

Last reply: Andrea Traber, Sep 29, 2010, 12:25 pm

Previously developed site?

CS-2009 SSc2: Development Density and Community Connectivity
posted by Reid Highley on Sep 14, 2010, 2:53 pm

I am working on LEED documentation for a project that meets all the requirements in Option 2 for community connectivity. The site has never had a building on it, however it has been graded,...

Last reply: Julie Hendricks, Sep 29, 2010, 12:09 pm

FTE for hotel guests

EBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiency
posted by Tanmay Tathagat on Sep 20, 2010, 7:40 am

The concerned project building is a five star hotel. Table3 in WE p1 mentions the default fixture usage for...

Last reply: Dan Ackerstein, Sep 29, 2010, 9:06 am

Preventive maintenance program

EBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiency
posted by Rachael McClain on Sep 13, 2010, 5:20 pm

I don't see where the preventive maintenance program is required for LEED submittals, is this just best management practices or actually required?