Hi, if we going to attempt this credit,do we need to implement IPM as well for the newly adapted vegetation?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forForum discussion
EBOM-2009 SSc5: Site Development—Protect or Restore Open Habitat
Hi, if we going to attempt this credit,do we need to implement IPM as well for the newly adapted vegetation?
LEEDuser is supported by our premium members, not by advertisers.
Go premium forTo post a comment, you need to register for a LEEDuser Basic membership (free) or login to your existing profile.
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11477 thumbs up
October 29, 2010 - 2:22 pm
No, not to meet the requirements of SSc5. You would have to do this for SSc3, however.