SS Credit 1, Option 2, Path 5 Heat Island Effect – RoofCI-2009 SSc1: Site Selectionposted by Augusto Velazquez on May 4, 2011, 9:24 am
I am working on a CI project. The project’s area is part of a large commercial facility which includes many other tenants. For the SS Credit 1 Option 2 Path 5... Last reply: Tristan Roberts, May 20, 2011, 2:28 am |
|
Is it possible to gain an ID credit by using Post Tensioning?NC-2009 IDc1: Innovation in Designposted by Amar Colakhodzic on Apr 28, 2011, 6:34 am
I am participating in a Value Engineering (VE) exercise for a potential LEED project that is in its final stage of design. Since the current project is designed as ‘concrete reinforced (CR)’, one... Last reply: Tristan Roberts, May 20, 2011, 2:26 am |
|
Storm water- Quality controlCI-2009 SSc1: Site Selectionposted by Sundararaj Subburaman on May 3, 2011, 10:56 pm
If a project has rainwater recharge pits located throughout the site can the project consider this as an infilteration Basin as listed in... Last reply: Tristan Roberts, May 20, 2011, 2:23 am |
|
FTE Calculation for Movie TheatresCalculating FTEsposted by Nilo Regojo on May 11, 2011, 12:33 pm
We are calculating... Last reply: Tristan Roberts, May 20, 2011, 2:18 am |
|
Baseline and design system selectionNC-2009 EAp2: Minimum Energy Performanceposted by Bala Srini on May 19, 2011, 10:39 am
Our semi industrial building's production area does not have cooling system, Proposed model simulated based on ASHRAE 90.1-2007, Table G3.1, 10. HVAC No. d “Where system exists or no cooling... Last reply: Marcus Sheffer, May 20, 2011, 1:44 am |
|
USGBC customer serviceGeneral forumsposted by Tristan Roberts on May 20, 2011, 12:13 am
Daniela, the company should have an account with USGBC.org, and an account admin who can log in and change details like names. If you have trouble finding this, I would contact USGBC customer... |
|
LEED certification for zooGeneral forumsposted by Tristan Roberts on May 20, 2011, 12:12 am
Erin, you cannot exempt a portion of the building in this way. You'll need to show savings in all areas of building eneryg use to earn LEED points. More information about this in the... |
|
Missing LEED information for some itemsCI-2009 MRc4: Recycled Contentposted by Sandra Eremic on May 11, 2011, 7:28 pm
There are a few items in my project for which LEED information is not available - like desk lamps, desk pads, hangers, coasters, even some fabrics. Can I still submitt for the credits? My guess... Last reply: Tristan Roberts, May 20, 2011, 12:02 am |
|
Materials- Core & ShellCS-2009 MRc5: Regional Materialsposted by Joaquim Lima on May 4, 2011, 1:31 pm
Good morning! my project is classified as Core & Shell, I wonder if the calculations for credit 5 (Materials and Resources) should consider only the materials used in the common areas... Last reply: Tristan Roberts, May 20, 2011, 12:00 am |
|
"Other Non-structural Elements" covered elsewhere??CI-2009 MRc1.2: Building reuse - maintain interior nonstructural elementsposted by Gail von Staden on Apr 27, 2011, 2:06 pm
The project we are working on is looking to take advantage of MRc1.2 Building Reuse. However, this credit seems to only cover the basic non-structural elements - walls, floors, ceiling etc.... Last reply: Tristan Roberts, May 19, 2011, 11:58 pm |