Topic | Recent |
---|---|
Combination low-emitting parking and car pooling spaces possibleCI-2009 SSc3.3: Alternative transportation - parking availabilityposted by Mark Frey on Feb 8, 2012, 5:36 am
In our C&S project the building owner provides 15 parking spaces for low-emitting and fuel-efficient vehicles. The main tenant will rent and use these parking spaces. Additionally we need for... Last reply: Tristan Roberts, Feb 21, 2012, 9:45 pm |
|
IEQc4.2General forumsposted by Tristan Roberts on Feb 21, 2012, 9:21 pm
Anatoly, please see the requiements and discussion under IEQc4.2—I think that's where this would fall. |
|
IAQ Concerns due to LEED boundaryCI-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Kunjan Shah on Feb 1, 2012, 5:03 pm
My project is inside a 3 story building. The remodel work spans all 3 floors and City permit drawings show work all over the building and building shell. My client wishes to restrict the LEED... Last reply: Tristan Roberts, Feb 21, 2012, 9:16 pm |
|
In a LEED certified buildingCI-2009 SSc2: Development Density and Community Connectivityposted by Aaron Yorke on Dec 23, 2011, 8:53 am
Hi all, We have a CI project in a CS v2009 certified project which achieved the development... Last reply: Tristan Roberts, Feb 21, 2012, 9:04 pm |
|
Partial Building Energy Star ScoreEBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by SIG - Sustainability Main Account on Feb 15, 2012, 9:44 am
I am analyzing a 40 story vertical mixed use tower for LEED... Last reply: Michael Opitz, Feb 21, 2012, 7:26 pm |
|
RebarSchools-2009 MRc4: Recycled Contentposted by Nell Achtmeyer on Feb 1, 2012, 4:15 pm
I have a question about tracking the... Last reply: Nell Achtmeyer, Feb 21, 2012, 6:33 pm |
|
Comments from a LEED reviewEBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioningposted by Raphael Sperry on Jun 3, 2011, 4:50 pm
We just received comments on a review of this credit I am trying to understand. For this project, we actually had an approved MV plan from LEED NC credit EAc5. The plan is very detailed and... Last reply: Jacob Arlein, Feb 21, 2012, 5:36 pm |
|
small back-up laundry in hotel?NC-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by Jutta Berns on Feb 20, 2012, 4:12 am
in our hotel project all laundry is outsourced to an external laundry service but we have a small area for back-up laundry requirements for the odd items that may have to be laundered. there will... Last reply: Jutta Berns, Feb 21, 2012, 5:19 pm |
|
Furniture ValueCI-2009 MRc4: Recycled Contentposted by severine secret on Jan 9, 2012, 5:16 pm
When documenting the furniture value of an order for credits MRc4 thru Mrc7, do we include local tax, installation and freight on the total order? The verbiage throws me off as it states all... Last reply: Tristan Roberts, Feb 21, 2012, 5:18 pm |
|
Flow restrictors / aerators documentationCS-2009 WEp1: Water Use Reductionposted by Petra Hajná on Feb 6, 2012, 9:05 am
Hi all! Last reply: Tristan Roberts, Feb 21, 2012, 4:51 pm |