Commercial Kitchen equipment commissioning

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Patrick Cellie  on 

I am working with a convention center currently certified Silver in the v2009 EBOM rating system. The owners are monitoring data with the goal to re-certify when the time comes.

3
Default Avatar
Sustainability Consultant
AECOM
LEEDuser Basic Member
0 thumbs up
Wed Jan 16, 2019, 4:09 pm

Breakdown of energy use

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Gustavo De las Heras Izquierdo  on 

It is required by the credit: "to document the breakdown of energy use in the building". Is it mandatory to have permanent energy meters by end use in order to meet this requirement? What other m

1
Tue Mar 25, 2014, 6:05 pm

Use of C&S Commissioning documentation

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Izabela Kwiecinska  on 

Hi Everyone, We are working on a building that already got LEED C&S certificate in 2012 and now aims to get EBOM.

1
Fri Feb 10, 2017, 8:56 pm

Level II audit

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Robert Calloway  on 

If you go the Level II route (in lieu of RCx), does uploading a level II audit for the level I audit suffice?

1
Fri Feb 22, 2013, 9:44 pm

Am i required to do the Level I first

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Chris Callas  on 

We are looking to do this in-house, we can document the study and record the findings. but as part of this credit do i need to show i performed the Level I first?

1
Wed Mar 5, 2014, 5:09 pm

Minimum number of equipments to be audited

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  ESD Singapore  on 

Hi all, The project that we are working on would like to go pursue this credit using ASHRAE level 2 commissioning audit path. However, this project has a large quantity of AHUs and FCUs (approx.

1
Fri Feb 1, 2013, 12:51 pm

Retrocommissioning - Systems Requirements

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Nate Eppley  on 

I am working on a cultural center performance space in San Diego with very few HVAC system components.

1
Tue Feb 15, 2011, 12:19 am

Existing Building Commissioning

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  sebastian castañeda  on 

Hello. I am a student who is interested in learning about the methodology of LEED certification and there are some points that I do not clear.

1
Tue Jun 21, 2016, 5:53 pm

CX EBOM EAc2.1

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Katherine Phelps  on 

Looking for a Building commissioning service provider in Southern Massachusetts.

1
Wed Oct 10, 2012, 9:09 pm

Update of the ASHRAE Level II Audit report

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  David ESPAGNET  on 

Hello everybody. The Ashrae Audit realized for the LEED EBOM project i am in charge was completed more than 2 years before the performance period.

1