Can the Project Management Consultant (PMC) act as the LEED Commissioning Authority (CxA)?
NC-v4.1 EAc1:Enhanced Commissioningposted by Hameed Jasir on
Hello everyone,
I would like to clarify a scenario related to the CxA eligibility requirements for LEED v4.1 Fundamental and Enhanced Commissioning.
BREAKING NEWS: Huge Change who the CxA can be in EAc1!
NC-v4.1 EAc1:Enhanced Commissioningposted by Scott Bowman on
Thank you LEEDuser for flagging this huge change to v4.1. In the latest addenda, there has been a change to the requirement for who the CxA can be on a project.
LEED Ceremonies at Opening Day
NC-v4.1 EAc1:Enhanced Commissioningposted by Kath Williams on
Is there any way under version 4.1to meet the requirements of this credit in a timely fashion so that the LEED Plaque can be awarded on the building's opening/ribbon cutting day? Enhance
BeCx - Ongoing commissioning plan
NC-v4.1 EAc1:Enhanced Commissioningposted by Manuelle Croft on
The commissioning authority must complete Enhance Cx tasks for the building(s)'s thermal envelope. An ongoing commissioning plan must be developped.
BECx & ASTM E2813 Standard - Fundamental vs. Enhanced building enclosure commissioning (BECx).
NC-v4.1 EAc1:Enhanced Commissioningposted by Shahrzad Pedram on
LEED v4.1 references ASTM standard E2813 Standard Practice for Building Enclosure Commissioning regarding BECx requirements.
Seasonal Commissioning in an area with no seasons like Singapore
NC-v4.1 EAc1:Enhanced Commissioningposted by Jordan Kirrane on
Does anyone know or have experience demonstrating that, Seasonal Commissioning, a requirement of the enhanced commissioning credit has been met in Singapore?