NC-v4 LTc3:High priority siteposted by Samuel Calhoun on
A project I am working on had (QTY: 27) above ground storage tanks removed from the site. This work was overseen by a 3rd party consultant, permitted by the local AHJ, and registered with the DEP.
Historical designation and infill site calculation
NC-v4 LTc3:High priority siteposted by Jacopo Cattaruzzi on
Hi,
High priority site
NC-v4 LTc3:High priority siteposted by Ahmed Hamed on
- How to apply Priority Designation option outside the U.S
Tools for Canada?
NC-v4 LTc3:High priority siteposted by emily reese moody on
Have y'all found any handy tools similar to the HUD or Opportunity Zone maps that we typically use for US projects...but for Canada?
Option 2: Priority Designation - local equivalent program
NC-v4 LTc3:High priority siteposted by N. Josef Nassif on
Dear Community
I hope you are doing fine.
I have a question regarding the Option 2 in high-Priority site. In LEED V4 it says:
Grounwater contamination at the campus level
NC-v4 LTc3:High priority siteposted by Bret Mantyk on
I'm working on a project that is considering pursing the LTc3 High Priority Site credit, Option 3 Brownfield Remediation at the campus level.
Project site part of a newly masterplanned area
NC-v4 LTc3:High priority siteposted by Nermin Hegazy on
Hello!
Timeline for priority designation
NC-v4 LTc3:High priority siteposted by David Hryvniak on
I'm working on a project which is on a site that was in a Qualified Census Tract in 2019. However, the site is no longer within a QCT.
Remediation of LEED Project Area or only disturbed areas
NC-v4 LTc3:High priority siteposted by Mark Meaders on
We have a project that has had a Phase 1 and II ESA performed. It found there was acetone and mercury on site.