Do not include land-clearing debris or excavated soil or rock in your calculations. Even if diverted from landfill, it is not to be included in the credit calculations. Contractors often think that trees and stumps are still part of the diverted waste, but take them out of the LEED credit form and supporting documentation if the contractor includes them.
Waste amounts must be tracked consistently, either by weight or volume. If materials are very heavy, it is best to use the weight approach. Most waste processors track by weight, anyway. But this will depend on what the bulk of the project’s waste is made of.
LEED project managers should provide contractors with tracking or log-book forms to simplify the tracking process. See the Resources section for the LEEDuser CWM tracking calculator.
Maintain a project log to input all the monthly reports in one place. This will track project waste recycling rates and provide an alert if the average is lower than the target of 50% or 75%. Address these shortfalls early in the process to ensure that final diversion rates can be met.