If my project uses a District Energy System (DES) is enhanced commissioning required for the DES?

Maybe. Consult Treatment of District of Campus Thermal Energy in LEED V2 and LEED 2009. Depending on the characteristics of your project, commissioning of upstream DES equipment may be required. Commissioning is required only for DES equipment utilized by the LEED project. For example, a project that utilizes district steam but not chilled water is only required to commission DES steam equipment. Commissioning of DES equipment can be performed by the owner of the DES equipment or by an independent third party.

Who can perform enhanced commissioning services?

Generally, the CxA for Enhanced Commissioning must not have any connection to the design or construction of the building.  The CxA can be a subcontractor to the design team or construction manager, but the preferred option is for CxA to be directly contracted by the owner. For more details on who can be the CxA, see the Design Development section of the Checklists tab.

How do I account for computers with multiple monitors on Portfolio Manager?

The number of monitors in the building does not impact the number of computers entered into Portfolio Manager. The value for computers should reflect the total number of personal computers and servers in the office space. For example, if the office space includes 10 PCs, 5 laptops, and 25 monitors, the input for Portfolio Manager is 15 PCs.

If you pursue the streamlined path for an Energy Star label, should the performance period for EAc6 match the 12-month time frame of the label?

For EAc6, the performance period should fall within 30 days of the latest performance period end date for all other credits and prerequisites. It should not follow the period of the Energy Star label associated with the streamlined path for EAp2.

What do I do if the number of building occupants, operating hours, or vacant space changes during the performance period?

When applicable variables change during the performance period, these changes must be recorded on Portfolio Manager to ensure accurate benchmarking of the building. When making updates to the space characteristics on Portfolio Manager, make sure to select “update” rather than “correct” and note the date when the updated space characteristic was first true. By selecting “update” the change in the building characteristic is only counted for the appropriate portion of the performance period rather than the whole thing.