Forum quick links
Trying to get EQc1 without installing a visible alarm
NC-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Ira Ben-Reuven on
We are working to certify a NC. The tenants will not allow us to install a alarm in the presence of the customer.
100% OA constant volume enthalpy heat recovery ventilator
NC-v4 EQp1:Minimum indoor air quality performanceposted by Noriko Nagazumi on
Hi, Our project is mechanically ventilated by 100% OA constant volume enthalpy heat recovery ventilator.
Non potable water source offsite
NC-2009 WEc1:Water Efficient Landscapingposted by Mario S. on
Our Project is a NC, part of a university campus. The campus is supplying the project with the pipeline for irrigation. all the water supplied by the campus is Non-potable / reused water.
Preferred Parking Spaces Allocation
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Mario S. on
Our project is a new shopping mall that includes retail shops, a supermarket, and restaurants. All parking spaces are located in basement floors (basement 1 to 6).
Addition to Existing Leed EBOM Building
posted by Max Neu on
Forgive me if this has been answered, I searched all over and can't find a definitive answer.
Lighting power allowance calculations for V4 ID+C Retail
Retail-CI-v4 EAp2:Minimum energy performanceposted by Joanna Peacock on
According to ASHRAE 90.1-2010, paragraph 9.6.2, an additional interior lighting power is allowed for the following categories: a) Decorative lighting (up to 1W/ft2) b) Merchandise lighting c) For
Final Report
NC-v4 EAc1:Enhanced commissioningposted by Colin Grist on
Hello all, I am wondering if there are guidelines for what should be included in the eCx final report. Is there a template or list of items that should be included? Thank you, Colin
renovation of multiple non-contiguous parts of an office
CI-2009 MPR2:Must be a complete, permanent building or spaceposted by Agnieszka Rylska on
The owner has a certified office which is located on a few floors of a building. Now he's going to renovate a part of it. On one floor there will be a few non-contiguous parts renovated.
An example of a ducument for Prerequisite 2
ND-Plan-v4 SLLp2:Imperiled species and ecological communitiesposted by oko Yael on
Hello Eliot, We are in a process of preparing the prerequisites documents for the first LEED ND project in Israel. All other prerequisites are technically clear. Prerequisite 2 is somehow softer.
Industrial zone
NC-v4 LTc3:High priority siteposted by Charalampos Giannikopoulos on
Would an officially designated industrial zone which provides tax incentives to businesses be considered as an eligible "high-priority site" to locate a project on? Thank you.