Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

V4 EBOM - Commissioning

EBOM-v4 EAc2:Existing building commissioning - implementation
posted by  Meier Corporate Account  on 

Good Afternoon, Our manufacturing plant was constructed in 2014-2015 and went online in August of 2015.

1
Mon Jun 20, 2016, 9:47 pm

What are the baseline conditions?

EBOM-v4 SSc5:Site management
posted by  Zachary Hayes  on 

This says we have to reduce from the baseline, which I assume is our initial reported use. However, if this is the case how can there be any reduction?

0

Modeling Procedure for ERV,HRW,Treated Fresh Air Units

NC-2009 EAp2:Minimum Energy Performance
posted by  SAMY Chamy  on 

Dear All we have model the factory project with 50% A/c and 50% Ventilation and the fresh air is supplied by ERV, HRW, Treated fresh air units to A/c areas but the ERV, HRW, Treated fresh air unit

1
Fri Jun 17, 2016, 1:02 pm

HVAC modelling for Tenant Occupied Spaces

CS-2009 EAp2:Minimum Energy Performance
posted by  Saumendra Aggrawal  on 

I am working on a project, which is going for LEED C&S. The project has tenant occupied space, which has designed HVAC system for it.

1
Sun Jun 19, 2016, 8:52 pm

Thermal Comfort - Adaptive Method

NC-2009 IEQc7.1:Thermal Comfort—Design
posted by  SAMY Chamy  on 

Dear All we are using (http://smap.cbe.berkeley.edu/comforttool) this link for thermal comfort results but we use PMV method for A/c areas and Adaptive method for ventilated areas (due to lack of

0

Thermal Comfort - Adaptive Method

NC-2009 IEQc7.1:Thermal Comfort—Design
posted by  SAMY Chamy  on 

Dear All:- As of now we are using berkeley.edu/comfort tool for thermal comfort compliance for both A/c & Non A/c area But we use PMV method for A/c area and adaptive method for Non A/c area

1
Thu Jun 30, 2016, 7:39 pm

dedicated wind farm

NC-2009 EAc6:Green power
posted by  Erin Holdenried  on 

I have a project with a dedicated wind farm. The wind farm is offsite, built by a 3rd party with a contract to supply 100% of the project's electricity usage for 10 years.

1
Tue Jun 21, 2016, 2:00 pm

Documentation

Healthcare-v4 MRp3:PBT source reduction - mercury
posted by  David Dixon  on 

Working on a v2009 BD+C project and using the credit as an ID credit looking for information on accepted documentation. Any insight will be helpful

1
Sat Aug 26, 2017, 3:27 pm

CASE 1 NON RESIDENTIAL OPTION 3

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Tim Gaidis  on 

Hi there, For our project in StJohn's, Newfoundland, we are providing 3 Barrier Free spaces and 3 Maintenance Parking spaces (for maintenance facility users to use, but are not always used). We w

1
Thu Jun 23, 2016, 11:22 pm

OPTION 3 METHOD

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Tim Gaidis  on 

Hi there, we are working on a project in St John's, Newfoundland and was wondering: 1. For Option 3 does Car Sharing only mean renting cars (i.e.

0