Option 1 | expressway as site used for industrial or commercial purposes

Warehouses-NC-v4 LTc4:Surrounding density and diverse uses
posted by  Agnieszka Rylska  on 

In Option 1 of the credit guidelines, there is the requirement that adjacent site must be currently used for industrial or commercial purposes.

1
Fri Nov 16, 2018, 11:47 am

ASHRAE 90.1 Lighting Controls

NC-v4 EAp2:Minimum energy performance
posted by  Charalampos Giannikopoulos  on 

Section 9.4.1.3 requires that lighting shall be controlled by one or more devices that automatically reduce lighting power of each luminaire by a minimum of 30% when there is no activity detected w

1
Tue Nov 20, 2018, 6:54 pm

produt labels

Homes-v4 MRc2:Environmentally preferable products
posted by  Charles Nepps  on 

Do products labeled Green Seal, Floor Score, etc. still meet the intent of this credit?

1
Wed Jan 16, 2019, 10:25 pm

Pilot Credit Forum Participation

Pilot-Credits IPpc101:Integrative Process
posted by  Craig Sheehy  on 

As per the requirements for this pilot credit we are noting our participation in the Forum.

1
Tue Nov 20, 2018, 8:21 pm

Project Boundary (Urban Environment) - Bike racks on sidewalk

CS-v4 LTc6:Bicycle facilities
posted by  Matthew Wang  on 

I have a commercial office building in Manhattan with retail on the ground floor.  The public sidewalk is excluded from the Project Boundary because it is outside of my property line and a pub

1
Thu Nov 15, 2018, 4:56 am

Contact local utility representatives to discuss participation in future DR programs

NC-v4 EAc4:Demand response
posted by  DAVE LI  on 

The local utility company did not provide a demand response plan.

3
Default Avatar
Delta Electronics
LEEDuser Basic Member
1 thumbs up
Wed Nov 14, 2018, 3:24 pm

Option 2 - threshold of 30% of the costs attributed Structure and Enclosure

CS-v4 MRc4:Building product disclosure and optimization - material ingredients
posted by  Barry Farren  on 

For Option 2, demonstrating that 25% of the cost of the project materials meet REACh compliance, There is a requirement that only 30% of these material costs can be attributed t

0

Mulitzone FCU with VAV

CI-v4 EQp1:Minimum indoor air quality performance
posted by  Gopinath Vasu  on 
Hi All, I am working in a project where FCUs (cooling only) system with VAVs are used to condition the group of spaces. The fresh air supply to the space is from TFA system.
0