Option 1 | expressway as site used for industrial or commercial purposes
Warehouses-NC-v4 LTc4:Surrounding density and diverse usesposted by Agnieszka Rylska on
In Option 1 of the credit guidelines, there is the requirement that adjacent site must be currently used for industrial or commercial purposes.
ASHRAE 90.1 Lighting Controls
NC-v4 EAp2:Minimum energy performanceposted by Charalampos Giannikopoulos on
Section 9.4.1.3 requires that lighting shall be controlled by one or more devices that automatically reduce lighting power of each luminaire by a minimum of 30% when there is no activity detected w
produt labels
Homes-v4 MRc2:Environmentally preferable productsposted by Charles Nepps on
Do products labeled Green Seal, Floor Score, etc. still meet the intent of this credit?
Pilot Credit Forum Participation
Pilot-Credits IPpc101:Integrative Processposted by Craig Sheehy on
As per the requirements for this pilot credit we are noting our participation in the Forum.
Storm Water Quantity and Quality in Washington DC
NC-2009 IDc1:Innovation in Designposted by Rodrigo Uribe on
Hi,
Background:
Project Boundary (Urban Environment) - Bike racks on sidewalk
CS-v4 LTc6:Bicycle facilitiesposted by Matthew Wang on
I have a commercial office building in Manhattan with retail on the ground floor. The public sidewalk is excluded from the Project Boundary because it is outside of my property line and a pub
Contact local utility representatives to discuss participation in future DR programs
NC-v4 EAc4:Demand responseposted by DAVE LI on
The local utility company did not provide a demand response plan.
Option 2 - threshold of 30% of the costs attributed Structure and Enclosure
CS-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by Barry Farren on