Topic | Recent |
---|---|
AHU FiltersNC-2009 IEQc3.1: Construction IAQ management plan - during constructionposted by Amruta Kshemkalyani on Apr 25, 2010, 12:53 am
Hi, we are MEP contractors in Abu Dhabi, working on LEED project. Last reply: Tristan Roberts, Apr 29, 2010, 11:12 am |
|
30% Increased ventilation issuesNC-2009 IEQp1: Minimum indoor air quality performanceposted by W. Edward Locke, CSI-CIAQP-M.SAME on Apr 23, 2010, 2:03 pm
The 30% increase in ventilation above ASHRAE 62.1-2007 is a good idea in dry climates. Our issuse is that we have several projects that are seeking LEED Silver with client (GSA) demanding the... Last reply: Roger Chang, Apr 29, 2010, 9:17 am |
|
LEED Rating System Selection PolicyGeneral forumsposted by Tristan Roberts on Apr 28, 2010, 10:51 pm
I assume you've also checked out the USGBC's LEED rating system selection policy, which can be found here? |
|
Extraction LocationsNC-2009 MRc5: Regional Materialsposted by Robin Kelley on Apr 26, 2010, 9:26 am
I am having difficulty getting extraction locations for materials used in roofing assemblys. Most suppliers submit this information as being unavailable due to various locations or unknown... Last reply: Tristan Roberts, Apr 28, 2010, 10:08 pm |
|
Green Label Plus, FloorScore and Option 2CI-2009 IEQc4.3: Low-emitting materials - flooring systemsposted by DOUG VAN ETTEN on Apr 27, 2010, 12:18 pm
Are you able to clarify the meaning of Option 2 and its relation to the footnotes in the credit guide? - Option 2 prescribes compliance with the "requirements of the California... Last reply: Tristan Roberts, Apr 28, 2010, 4:27 pm |
|
IOc1 Exemplary Performance, multiple EP points for EAc4EBOM-2009 IOc1: Innovation in Operationsposted by Ryan Schwabenbauer on Apr 28, 2010, 2:06 pm
Could you achieve multiple Exemplary Performance Points by exceeding a credit by multiple thresholds? Or can you achieve only one EP point per existing credit? Example: LEED... Last reply: Tristan Roberts, Apr 28, 2010, 3:09 pm |
|
LEED Online credit form says toNC-2009 WEp1: Water Use Reductionposted by Armen Khachikyan on Apr 28, 2010, 7:24 am
The LEED Online credit form says to "provide the plumbing fixture and fitting schedule for the project highlighting flush and flow rates for all applicable plumbing fixtures and fittings". What... Last reply: Dave Intner, Apr 28, 2010, 11:43 am |
|
Core fixtures included?CI-2009 WEp1: Water Use Reductionposted by Jonathan Gritz on Sep 5, 2009, 11:00 am
I'd like to hear other people's opinions on this direction included above: Last reply: Devon Bertram, Apr 28, 2010, 1:06 am |
|
Artificial TurfNC-2009 SSc7.1: Heat island effect - nonroofposted by Alexis Voeltner on Apr 27, 2010, 7:25 pm
There are many artificial turf manufacturers that claim their artificial turf satisfy multiple LEED credits. Can artificial turf be considered “open-grid pavement system” under credit SS 7.1:... Last reply: Tristan Roberts, Apr 27, 2010, 8:13 pm |
|
Water info?EBOM-2009 EAp2: Minimum Energy Efficiency Performanceposted by Rachael McClain on Apr 27, 2010, 2:43 pm
Hi, I was wondering if you need water bills to generate a Energy Star Rating. The Reference guide says "The energy data must include data from electricity, natural gas, fuel oil, diesel fuel,... Last reply: Corinna Kester, Apr 27, 2010, 2:48 pm |