posted by susan eguia on Oct 29, 2012, 11:26 am

Hi,

We've got the review comments from USGBC that says:

"Please provide a separate ventilation rate procedure calculation for each multiple-zone recirculating system serving the...

Last reply: Hernando Miranda, Nov 7, 2012, 12:34 pm

Millworker/Casework Installer CoC

NC-2009 MRc7: Certified Wood
posted by Michelle Rosenberger on Oct 29, 2012, 3:13 pm

We are now seeing review comments about millwork or casework subs not having...

Last reply: Furniture Assembly Team, Feb 5, 2019, 12:05 am

Where can I find the VOC limits for sealants used as fillers?

EBOM-2009 SSc2: Building Exterior and Hardscape Management Plan
posted by yan lian on Oct 30, 2012, 3:30 am

Our review comments has one item,
"Provide a revised plan that includes sustainability criteria for...

Last reply: Michelle Raigosa, Aug 19, 2013, 8:38 pm

CASE 3- pedestrian-oriented hardscape area & 25% vegetated area

CS-2009 SSc5.2: Site development - maximize open space
posted by Michal Marszalek on Nov 3, 2012, 6:11 am

Hi

I have a question about this description: pedestrian-oriented hardscape areas can contribute to credit compliance. For such projects, a minimum of 25% of the open space counted must be...

Last reply: Yoyo Shek, Mar 22, 2019, 5:43 am

Ohio Investment in Green Schools Not Spurious

General forums
posted by Nadav Malin on Nov 6, 2012, 9:28 am

The Ohio Green Building Law blog has a story describing the anticipated ROI of the $131 million investment in green schools that the USA Today story criticizes.
...

Last reply: Bill Swanson, Dec 6, 2012, 8:23 am

Energy modeling- Adjacente building

NC-2009 EAp2: Minimum Energy Performance
posted by Luana Bertoletti on Nov 7, 2012, 11:55 am

Hi,

I have a doubt when modeling proposed and baseline building.

If I have some adjacent buildings to the proposed model, should I include their geometry in the proposed/baseline...

Last reply: Luana Bertoletti, Sep 10, 2013, 2:47 pm

Total daily occupancy, adjusting peak number in table Plf3-3

NC-2009 PIf3: Occupant and Usage Data
posted by Tom O'Neil on Nov 18, 2012, 12:52 pm

My project has completed the initial review and I now realize that the peak transient occupancy number I listed in table Plf3-3 is incorrect. I cannot change the number because the section is...

Last reply: Tom O'Neil, Nov 20, 2012, 10:12 am

Pool Complex EAp2

EBOM-2009 EAp2: Minimum Energy Efficiency Performance
posted by Emilio Rovira on Nov 19, 2012, 3:18 pm

energy usage; simulation results are disallowed. They might accept the sub-metered data for Ravi's purpose of deducting the pool loads, but unless someone else on this forum has had success doing...

Last reply: David Eldridge, Feb 14, 2013, 3:21 pm

RSF & Gross SF

NC-2009 PIf2: Project Summary Details
posted by Sheela I on Nov 21, 2012, 1:07 pm

LEEDuser Experts to provide in our free forum. May I suggest bringing in some consulting help from Kim, or another expert? You can reach her via her profile page on LEEDuser. Thanks! Log in or register...

Last reply: Sheela I, Nov 26, 2012, 10:34 am

Calculation of baseline

Healthcare-v2009 WEc2: Water use reduction - measurement and verification
posted by Emil Andersson on Nov 26, 2012, 9:22 am

Hi.

Does anyone have any experience how the baseline calculation for the M&V-plan can be established? Are there any software available or can the calculations for WEp1 together with...

Last reply: Keerthana Gopinath, Apr 18, 2018, 2:55 am