Chiller Selection for Baseline

NC-2009 EAc1:Optimize Energy Performance
posted by  Poorva Keskar  on 

We are working on a project where the total project has five towers on one podium. We are certifying only one tower for LEED-NC with an area of 34152 sq.m.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Aug 28, 2013, 1:47 am

Chemical storage room with recirculating HVAC cooling system

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Maya Karkour  on 

Hello, One of the LEED requirements of this credit is: "[For rooms with chemicals / hazardous gases], the exhaust rate must be at least 0.50 CFM per sq. ft.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Aug 28, 2013, 12:50 am

Warning for net-zero projects.

NC-2009 EAc6:Green power
posted by  Hernando Miranda  on 

The GBCI has decided that net-zero projects must buy additional EAc6 green power if the actual energy use for two-years post-occupancy does not match the GBCI approved results from EAc1/EAc2.

4
Wed Aug 28, 2013, 12:38 am

Green Roof over an underground parking garage

NC-2009 SSc7.2:Heat Island Effect—Roof
posted by  adi ashkenazi  on 

Can I calculate the green roofs over an underground parking garage? (I calculated them as part of the landscape for SS CR 7.1-non roof) Thanks

2
Partner, Architecture & Sustainability
DIALOG
LEEDuser Premium Member
449 thumbs up
Tue Aug 27, 2013, 11:27 am

Online documentation clarification

NC-2009 SSc1:Site Selection
posted by  BABAR MEHMOOD  on 

As i checked online submittal template, it seems that we only have to mark the check box, do we have to need to submitt any documentation for the requirements mentioned in this credit.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Tue Aug 27, 2013, 9:14 am

DES should be encourage!

NC-2009 EAc1:Optimize Energy Performance
posted by  jose Babilonia  on 

We are modeling a new LEED school building that is an addition of an existing complex buildings. The simulation was made using HAP.

3
Mon Aug 26, 2013, 7:46 pm

LEED V.4 and LEED AP Exams

General forums
posted by  Hasitha Herath  on 

i heard that LEED V.4 is on the way. i am planning to take LEED AP (BD+C) exams in end of September? since LEED V4 is coming will there be changes to the scope of the exam?

3
Director of Sustainability
Leopardo Companies, Inc.
LEEDuser Premium Member
12 thumbs up
Mon Aug 26, 2013, 4:30 pm

LEED Online Form for MR Cr. 4 used V 3 to convert to V 4

NC-2009 MRc4:Recycled Content
posted by  Benjie Herrera  on 

The LEED online V3 form of MR Cr 4 requires to type item by item sustainable materials on the form while V4 form requires only to upload material calculator worksheet and then type the total cost

2
Mon Aug 26, 2013, 1:41 pm

Line of Sight from Workstations

NC-2009 IEQc8.2:Daylight and Views—Views
posted by  Andrew Ellsworth  on 

I have two questions that may seem nitpicky, but are relevant to achieving this credit.

3
Default Avatar
Ellsworth Building Portfolio Services
LEEDuser Basic Member
3 thumbs up
Mon Aug 26, 2013, 1:22 pm

green house and daylighti credit

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Oleg Petryuchenko  on 

We have large warehouse project that also has a green house as a part of the building. could this area be excluded from daylighting?

4
Fri Aug 23, 2013, 10:14 pm