exterior lights in enclosed courtyardNC-2009 SSc8: Light Pollution Reductionposted by Erin Holdenried on Dec 20, 2012, 2:50 pm
I have a project where the only exterior lights are within a courtyard that is surrounded by the building on all sides, 4 storys tall. Would the project still have to submit a photometric plan?... |
|
Hotels achieving this credit?NC-2009 SSc8: Light Pollution Reductionposted by Nelina Loiselle on Jan 11, 2013, 4:25 pm
Has any one worked on/heard of a hotel project that was able to achieve this credit? There doesn't seem to be a clear answer on whether or not hotels are exempt from the interior lighiting... |
|
SSc8 for Multiple buildingsNC-2009 SSc8: Light Pollution Reductionposted by Marcio Alberto Casado Pereira on Feb 22, 2013, 9:36 am
We are trying to pursue this credit as a campus credit. However, 1 out of the 4 buildings we are certifying within the LEED Campus Boundary doesn't comply because it's 24hs, luminaires have a... |
|
Sports Field Lighting (floodlighting) power densitiesNC-2009 SSc8: Light Pollution Reductionposted by Ameet AA on Feb 28, 2013, 5:59 am
I am working on Football Club Academy project based on LEED NC 2009 and AGMBC 2011. My understanding is that the lighting power... |
|
light trespass on parkingNC-2009 SSc8: Light Pollution Reductionposted by Emmanuel Pauwels on Mar 11, 2013, 10:45 am
Our Project has a LEED boundary that crosses a parking lot. This means that half of the parking lot is within the leed boundary and the other half is outside the leed boundary. In order to comply... |
|
SS CREDIT 8:LIGHT POLLUTION REDUCTION- UPLIGHT ALLOWANCENC-2009 SSc8: Light Pollution Reductionposted by JUNE KOO KANG on Mar 14, 2013, 3:48 pm
I have a adjustable fixture mounted on the ground to uplight the tree. The initial fixture lumen above 90 degrees from nadir is 0 which is full cut off fixture. How can I... |
|
PhotometricsNC-2009 SSc8: Light Pollution Reductionposted by Saju Varghese on Mar 14, 2013, 4:33 pm
Can photometric plan be created with trees in it to avoid the leakage of... |
|
Facade lightingNC-2009 SSc8: Light Pollution Reductionposted by Jens Apel on Mar 15, 2013, 5:00 am
I do not understand if facade lighting is allowed and under what circumstances. When the requirement is "Light areas only as required for safety and comfort" this means to me that essentially... |
|
Boundary Lights: Not Allowed?NC-2009 SSc8: Light Pollution Reductionposted by Nowfal Kunju Muhammed on Apr 2, 2013, 9:27 am
If project uses boundary lights (even near to boundary also), it is very difficult to comply the credit requirements. Is there any solution to this issue? |
|
Changes in site lighting fixtures due to Value EngineeringNC-2009 SSc8: Light Pollution Reductionposted by Amit Ahiel on Apr 10, 2013, 8:07 am
I'm working on a project that already submitted for Preliminary Design review. After the review the contractor and client value engineered much of the site lighting to use all LEDs, instead of... |