Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Sediment Basin / Trap

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Samer Alhmdan  on 

Can we use the Infiltration Pond which is originally design for storm water collection during the operation phase of the project, can we use it as sediment trap during construction phase, noting th

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Sun Jun 1, 2014, 1:22 pm
5
Director, Sustainable Buildings and Operations
KEMA
LEEDuser Basic Member
46 thumbs up
Fri May 30, 2014, 12:41 pm

recycled % of steel

CS-2009 MRc4:Recycled Content
posted by  Vivien Wong  on 

Hi, we are estimating recycled % of steel, and would like to know if the estimation as shown below is correct or not: 1) steel with catalogue/declare letter showing %postconumer and %preconsumer:

2
Default Avatar
LEEDuser Expert
472 thumbs up
Fri May 30, 2014, 8:31 am

Fire Station FTE

NC-2009 PIf3:Occupant and Usage Data
posted by  Rosemary Muller  on 

Can you verify that FTE requested in PI form 3 is actually FTE per shift?

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Fri May 30, 2014, 4:01 am

applying for the Certification before or after the 10 months

CI-2009 EAc2:Enhanced Commissioning
posted by  Carolina Vergnano  on 

My doubt is if it´s possible to Certificate a building with the Operation and Maintenance Manual made by the CxA, or if it´s needed to wait the 10 months required for the Enhanced Commissioning. Wo

6
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Fri May 30, 2014, 1:13 am

LEED CI V2012

CI-2009 IDc2:LEED Accredited Professional
posted by  Jaewan Lee  on 

Dear APs I am curious of LEED CI ID category about Accredited Professional points. If I am LEED AP specialty in BD+C then can I still apply to the AP credit? Or should I have certain certification

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu May 29, 2014, 11:43 pm

Alternative Transportation

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  GOVINDACHARI SUNDARARAJAN  on 

The alternate transportaion specified 2 Bus Lines with in 1/4 Mile distance from site, it is specifed as 2 lines, kindly confirm that this site should be accesible for 2 different bus routes or sim

2
Thu May 29, 2014, 10:45 pm

Chain of custod?

NC-2009 MRc7:Certified Wood
posted by  Jennifer Ratts  on 

i am working on a project where a fabricator (who has a CoC) has used another company to assemble a wood cabimet.

4
LEED-AP BD+C
GREENSQUARE
LEEDuser Expert
261 thumbs up
Thu May 29, 2014, 10:03 pm

Pesticides and herbicides

Healthcare-v2009 IEQc5:Indoor chemical and pollutant source control
posted by  Gustavo De las Heras Izquierdo  on 

The credit literature states: "Minimize the entry of contaminants into the building from vehicles, pesticides, herbicides, [...]" I wonder if the source of pesticides and herbicides should be con

3
Thu May 29, 2014, 5:39 pm

Self-level Screed Underlayment

CS-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Meghan Ward  on 

Does anyone know if a screed that is applied to concrete slabs prior to installing carpet tiles is considered for this credit and or IEQc4.1/4.2?

2
Thu May 29, 2014, 3:55 pm