WEc2 Regional Priority CreditEBOM-2009 RPc1: Regional Priorityposted by Kevin Wilcox on Aug 26, 2011, 5:37 pm
I have a EBOM... Last reply: Susan Walter, Aug 29, 2011, 11:07 am |
|
% of annual rainfall treated?NC-2009 SSc6.2: Stormwater design - quality controlposted by Kash Boodjeh on Aug 22, 2011, 3:06 pm
The reference guide states that "90% of the avg annual rainfall is equivalent to treating the runoff from 1" of rainfall for a... Last reply: Gregory Hurst, Aug 26, 2011, 6:09 pm |
|
Parking Lighting not through Building Elect ServiceNC-2009 SSc8: Light Pollution Reductionposted by Michelle Rosenberger on Aug 26, 2011, 4:56 pm
My project puts a new community center on an existing masterplanned campus. My LEED boundary includes new and relocated parking that serve the new building and are part of my project team's scope... |
|
LEED CS 2009 LEED ENERGY MODELCS-2009 EAc1: Optimize Energy Performanceposted by John Harrington on Aug 24, 2011, 5:14 pm
My proposed system is a WSHP. However, the heat from electric exceeds the heat used from boiler in the WSHP loop. I would condiser the primary heating source in this building to be... Last reply: John Harrington, Aug 26, 2011, 4:45 pm |
|
ASHRAE/eQuest question- external blinds and SHGC requirementCS-2009 EAc1: Optimize Energy Performanceposted by Agnes Vorbrodt on Jul 17, 2011, 12:09 pm
Hello, Last reply: Marcus Sheffer, Aug 26, 2011, 3:14 pm |
|
Can 10' requirement be met by a combination of mats?Schools-2009 IEQc5: Indoor Chemical and Pollutant Source Controlposted by Renee Shirey on Aug 26, 2011, 2:58 pm
Due to space constraints, our vestibules were not able to be a full 10' wide between our doors, thus the recessed walkoff mats aren't 10'. Does anyone see any issue with supplimenting the... Last reply: Allison Beer McKenzie, Aug 26, 2011, 3:03 pm |
|
Peak Demand Reduction Credit NOT Demand ResponsePilot-Credits EApc8: Demand responseposted by Debra Lombard on Aug 26, 2011, 1:15 pm
HI Everyone, I am working on a LEED-NC v2.2 project which is small but has three technologies that reduce... |
|
Secret LeaseCI-2009 MRc1.1: Tenant space - long-term commitmentposted by David Edenburn on Jul 19, 2011, 11:25 pm
In MR c1.1 and in other credits LEED asks for a (redacted) copy of the lease for term, utility payments, etc. In our case we have been told that the entire lease is confidential and cannot be... Last reply: Nadav Malin, Aug 26, 2011, 12:41 pm |
|
About Option 3: MeasurementCS-2009 IEQc8.1: Daylight and views - daylightposted by Diego Prada on May 5, 2011, 4:02 pm
Hello, If one decides to use option 3 to show compliance with this credit, should the light measurements have to be done in a specific time of the day? This doesn't seems to be the case,... Last reply: TODD REED, Aug 26, 2011, 10:13 am |
|
is a closed landfill automatically a brownfield?NC-2009 SSc3: Brownfield Redevelopmentposted by Amanda Redmond-Neal on Aug 12, 2011, 1:42 pm
My project is to be built on top of a landfill that was closed in 1961. I have a very comprehensive "Final Closure and Post-Closure Maintenance Plan" that details required monitoring of the site... Last reply: Larry Sims, Aug 26, 2011, 9:28 am |