Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

10% exemption for fire suppression systems

EBOM-2009 EAc5:Enhanced Refrigerant Management
posted by  AtSite Inc  on 

Is is possible to exempt 10% of the floor area that has CFC/halon/etc containing fire suppression systems?

1
Thu Oct 6, 2016, 3:29 pm

LPD for manufacturing space

NC-2009 EAp2:Minimum Energy Performance
posted by  Panupant Phapant  on 

Hi everyone, The project is cosmetic and medicine manufacturing with office. My question is, What difference between detailed manufacturing and Low/High Bay in ASHRAE90.1-2007 table 9.6.1?

1
Fri Sep 23, 2016, 2:49 pm

Fan power in conditioned space

NC-2009 EAp2:Minimum Energy Performance
posted by  Panupant Phapant  on 

Hello, My production line space in our project have an supply fan, exhaust fan and make-up fan to supply OA in conditioned space.

1
Fri Sep 23, 2016, 6:28 pm

Air Barrier Testing- Commercial

EBOM-v4 EAp2:Minimum energy performance
posted by  Justin Tyrrell  on 

Hi, I work for a company that currently does thermal bypass inspections and air barrier testing on single family and multifamily new construction projects.

1
Wed Oct 5, 2016, 5:39 pm

100% OA Laboratory System

NC-v4 EAp2:Minimum energy performance
posted by  Charles Daze  on 

I have a HVAC system with labs on it requiring 100% outside air systems. Following all the guidance in 90.1 these spaces require a dedicated Sys 5/7 because they are over 5,000 cfm.

1
Thu Oct 6, 2016, 3:05 pm

Self adhesive carpet

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Omar Elrawy  on 

We are using CRI certified carpet that directly adheres to the installed ceramic tiles, so we don't add any adhesives or sealants on-site.

0

Filtration Change Prior to Flush-out

NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Marcia Weekes  on 

On one project, the GC replaced construction filters at AHUs with final filters two months ago. However, delays in TAB and commissioning has delayed the start of the building flush-out.

1
Wed Jan 18, 2017, 5:10 am

Tri-gen

NC-v4 EAp2:Minimum energy performance
posted by  Victoria Watson  on 

Hi, I am QA'ing a model for a building that will be fed via a cogeneration plant (with absorption chillers) and therefore is a little complicated.

1
Mon Oct 31, 2016, 7:30 pm

DOAS

NC-2009 IEQp1:Minimum IAQ Performance
posted by  Kathryn West  on 

I have project with a dedicated outside air system that introduces air directly to the spaces on all levels (i.e. neutral air). The project has more than 100 VRF units.

1
Wed Sep 28, 2016, 10:58 pm

Dorm projects

NC-2009 IEQc7.2:Thermal Comfort—Verification
posted by  Brightworks Sustainability  on 

Hi all, I know this question was answers in various places but for a dormitory that has individual control in units for heat only but not air conditioning (operable windows only), can we still impl

1
Thu Dec 15, 2016, 3:59 pm