I have a HVAC system with labs on it requiring 100% outside air systems. Following all the guidance in 90.1 these spaces require a dedicated Sys 5/7 because they are over 5,000 cfm. Also my proposed design varies lower than 50% during unoccupied times with air quality sensing.

It is my understanding that the baseline should not vary less than 50% and I can show savings for that difference.

I have seen other comments on the internets about that difference in airflow not being allowed to be OA. Is this accurate? This seems illogical to me on a 100% lab system. Why would be baseline get savings potential of being able to return lab air?

Anyone have any insight on modeling Lab systems for LEED.

-Thanks