Forum quick links
Emergency lights
EBOM-2009 MRc4:Sustainable Purchasing—Reduced Mercury in Lampsposted by Saju Varghese on
Do emergency lights need to be included in this list?
LEED for a mixed use building
posted by Phyllis Biagi on
We have a client who is looking at a project which will consist of four stories of apartments over retail.
Products with Recycled Content
CI-2009 MRc7:Certified Woodposted by Lara Schneider on
Ok, from what I am gathering, wood products with both recycled content and FSC mixed cannot count for both MR4 and MR7, correct?
Wood deck SRI
NC-2009 SSc7.2:Heat Island Effect—Roofposted by Vanessa Bermudez on
I am working on a project registered under LEED NC 2.2. The roof includes a wood deck and I have not been able to find the SRI for wood. Any suggestions?
Server/ Computers in Data Centre
CI-2009 EAp2:Minimum Energy Performanceposted by Anthea Ng on
We have an interior renovation of works in a datacentre aiming for LEED-CI certification. The project area is managed and owned by the same client.
Kitchen Exhaust Make-Up Air
NC-2009 IEQp1:Minimum IAQ Performanceposted by Aaron Gary on
Can the make-up air (CFM) provided for a kitchen hood exhaust system be considered as part of the total OSA CFM, in the VRP calculation?
Timing of blower door tests
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Ilana Judah on
When can the blower door test take place? Can it be done when the drywall has been completed or do the cabinetry and appliances need to be installed as well?
College campus LEED boundary
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Jason Roberdeau on
We are working on a new residence hall which is located between two existing (non-certified) residence halls on a college campus.
Remediating to "residential (unrestricted) use"
Healthcare-v2009 SSp2:Environmental site assessmentposted by Kathy Wislocky on
Is it feasible for a LEED HC project to meet this prerequisite without being remediated to a "residential (unrestricted) use?" After speaking with our environmental consultant, this would require
Energy Performance Period - ATC Operation & Programing Problems
EBOM-2009 EAc1:Optimize Energy Performanceposted by James Doyle on
On an upcoming LEED EBOM project approaching the performance we have had lots of problems with the exclusive ATC contractor (a major international company) correcting control and programing problem