On an upcoming LEED EBOM project approaching the performance we have had lots of problems with the exclusive ATC contractor (a major international company) correcting control and programing problems for years. We have the ability to remotely operate the facility, ID problems, request ATC corrections and meet the energy savings through operational overrides during the performance period. We are a seasoned commissioning provider and will be using Cx documentation but the client does not want to pursue Cx credits at this time as financial limitations are limiting them to certified level only.
If we can have in place an improved maintenance contractual agreement such that the ATC provider will make “timely permanent” corrections from now through the performance period and we document their compliance through an Issues Log corrections list. Would this be an acceptable performance period process for EAp and EAc1 requirements?