Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Gross Floor Area, Mechanical Space

NC-2009 PIf2:Project Summary Details
posted by  Gary Ashford  on 

ASHRAE is not specific about deducting for floor openings. For cost estimating and code review, we normally deduct elevator shafts and stairwells.

1
Tue Jul 16, 2013, 7:36 pm

Non-potable water sources

NC-2009 WEc1:Water Efficient Landscaping
posted by  Inés Alomar  on 

We are participating in the certification of a building in the Europe Square in L’Hospitalet, Barcelona. The Europe Square area was previously and industrial area.

1
Sun Nov 3, 2013, 6:59 pm

ID for Green Walls

NC-2009 IDc1:Innovation in Design
posted by  Maya Karkour  on 

Hello, We are consulting on a large shopping mall and the Client will be covering one of the building facades with vegetation (roughly 25% of the vertical walls area will be covered). Do you thin

1
Sat Jul 20, 2013, 2:43 pm

Peak Demand...hourly, daily, weekly, monthly

NC-2009 EAp2:Minimum Energy Performance
posted by  Jean Marais  on 

Common sense tells me they are not interested in by the second peak energy demands for each end user...so to ask the stupid question: Which average value should I output here...hourly average annua

1
Wed Jul 3, 2013, 1:57 pm

Update of the energy modelling for the construction review

CS-2009 EAc1:Optimize Energy Performance
posted by  Juliette Barach  on 

Hi, I'm currently working on a LEED CS office building, and can't find a clear answer to my question in the LEED referential, user's guidance or standard: Do I need to update the energy modellin

1
Mon Jul 8, 2013, 2:38 pm

Lines of sight depth cutoff

CS-2009 IEQc8.2:Daylight and Views—Views
posted by  Matthew Macko  on 

Is there a requirement for the depth of lines of sight to exterior glazing to be compliant with this credit?

1
Mon Jul 8, 2013, 12:20 pm

FSC Wood Delivery Limits for Chain of Custody

NC-2009 MRc7:Certified Wood
posted by  Jennifer Kissinger  on 

I have a tradesman telling me that he can only make four deliveries to the jobsite for FSC certified materials in order to be compliant with chain of custody. Is this correct?

1
Wed Jul 3, 2013, 7:45 pm

EVSE requirement

Pilot-Credits LTpc70:Green vehicles
posted by  Yoyo Shek  on 

As in the requirement, EVSE must be networked and internet addressable and be capable to encourage off-peak charging.

0

PIF1 Review Comment Pre-Certification

NC-2009 PIf1:Minimum Program Requirements
posted by  Markus Henning  on 

We recive the following review comment in a pre certification on one of our CS projects.

1
Tue Jul 16, 2013, 7:34 pm

Question about the results in Performance Period

EBOM-2009 EAp2:Minimum Energy Efficiency Performance
posted by  Ron Dean  on 

There is a possibility that in the 12 months of the Performance Period, during the first six months not obtained satisfactory results provided the measures and strategies to achieve the minimum sco

1
Fri Jul 12, 2013, 10:48 pm