Critical Peak Pricing

NC-v4 EAc4:Demand response
posted by  RDK E&S  on 

I'm wondering if enrolling in a critical peak pricing tariff would qualify for this credit.

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Thu Oct 26, 2017, 3:50 am

Table 1.4.7B - Proposed Air-Side HVAC System Schedule - Outdoor Airflow cfm

NC-2009 EAp2:Minimum Energy Performance
posted by  Maria Spastri  on 

Hi,

I need a couple of clarificaitons regarding the Outdoor Airflow that has to be listed in Table 1.4.7.B of the proposed systems. The project is located in California.

3
Default Avatar
Sustainability Consultant
AECOM
LEEDuser Basic Member
0 thumbs up
Wed Oct 25, 2017, 7:58 pm

LEEDv4-NC "Detailed" Checklist: does this exist?

LEED Rating System Selection
posted by  Erica Downs  on 

Posting here because I'm not sure where else to... 

3
LEED for Homes Techincal Development
US Green Building Council
LEEDuser Expert
38 thumbs up
Tue Oct 24, 2017, 4:02 pm

Saguaro Ribs

NC-2009 MRc7:Certified Wood
posted by  Cindy Quinn  on 

I have a project that is using saguaro ribs as one of its building materials.  Do these ribs count as wood, and therefore need to be included in the total wood cost for MRc7?

1
Thu Oct 19, 2017, 2:58 am
3
Default Avatar
Designer
Rinkachung Architecture
LEEDuser Basic Member
1 thumbs up
Wed Oct 18, 2017, 4:09 pm

OA Monitoring for DOAS serving several HPs

NC-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Logan Dorrell  on 

For Case 1, Type 2, where at least 20% of the system serves non-densely occupied zones, we have a situation where (1) dedicated outside air system (DOAS) serves several smaller heat pump (HP) zones

4
Tue Oct 17, 2017, 8:52 pm

Rainwater Management GI

NC-v4 SSc4:Rainwater management
posted by  Jamé Wills  on 

Is Exfiltration Trench/French Drains a Green Infrastructure Method?

0

Secure Facilities

Schools-NC-v4 SSc8:Joint use of facilities
posted by  Lisa Logan  on 

Is it no longer a requirement to lock down parts of the building in order to meet this credit?

0

Running Exhaust Into Energy Recovery Wheel

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Neil Sen  on 

Are we allowed to run exhaust from areas like trash rooms into an energy recovery wheel and still achieve this credit?

3
Fri Oct 13, 2017, 7:36 am

Rainwater Management through BMP

NC-v4 SSc4:Rainwater management
posted by  Jamé Wills  on 

I have an 8 acre site that is largely buildings and roadway, is it possible to achieve this credit with the use of French drain (exfiltration trenches)?

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Thu Oct 12, 2017, 8:52 pm