Option 2 (prescriptive path) documentation?
NC-v4 EAp2:Minimum energy performanceposted by Erica Downs on
I have a project attempting EAp2/c2 via the prescriptive pathway, Option 2, 50% AEDG. The only "required documentation" listed in the Reference Guide is the completed AEDG tables, which seems
Option 1 Lighting Control - Undeveloped Future Tenant Spaces
NC-v4 EQc6:Interior lightingposted by James Keohane on
I am working on a project that has the majority of individual occupant spaces that will be completely finished with lighting controls meeting the requirements for Option 1. However, we a
Base Building Supplying Racks
CI-v4 LTc4:Bicycle facilitiesposted by Jane Christen on
We're working on a LEEDv4 Commercial Interiors project in Seattle, WA. Does it matter if the base building is supplying the short term bicycle racks?
Water Fountain / Bottle Filler + Wash Fountain Classifications
NC-v4 WEc2:Indoor water use reductionposted by Cammie Epstein on
1) Does a water fountain / bottle filler not count towards indoor water use? There's no option to list them under flow fixtures in the calculator. What am I missing?
Can you add credits after a LEED Construction Preliminary
posted by Summer Gorder on
We would like to add new credits that we did not originally submit for in our LEED Construction Prleominary review. Will the reviewer add the newly attempted credits?
Additions
NC-v4 MRc1:Building life-cycle impact reductionposted by Lorax Partnerships on
Our project is an addition built into the crotch of an L-shaped building.
Project in a resort attached to casino that allows smoking
NC-v4 EQp2:Environmental tobacco smoke controlposted by Anna Kaelin on
I have a client planning a complete fit-out of one of their retail spaces. The project is located in a resort in Las Vegas, which is attached to a Casino that allows smoking.
Single LEED building in Zoo: Demand Response Plan required for entire Zoo?
NC-v4 EAc4:Demand responseposted by Joyce Kelly on
Wondering if the Demand Response Plan needs to address the entire Zoo the way Parking, Green Vehicles credits must.
Including space in the the project boundary where only one trade is included in scope
CI-v4 MPR2:Must use reasonable LEED boundariesposted by Edgar Arevalo on
I have an ID+C project that takes up approximately half of a floor in a building. When laying out the LEED project boundary, I was confused as to whether to include the restrooms, since it wa