Status message
LEEDuser's Study Guide to the LEED v4 Green Associate Exam added to your cart.FTE for university facility
posted by Nadia Bini on
Our project is a University educational facility aiming for LEED-Canada 2009 (v3) certification. LEED stipulates that students are to be considered temporary occupants, however we anticipate that
LEED v4 CxA
NC-v4 EAp1:Fundamental commissioning and verificationposted by P. Hardy on
In LEED v4, the CxA for Enhanced Commissioning must be independent of the design and construction team- but what if the construction team is also the owner, as in design-build?
Green Cleaning as NC ID credit
EBOM-2009 IEQp3:Green Cleaning Policyposted by Jordan Kirrane on
Hi, I am pursuing Green Cleaning as an ID credit for a NC v3 building. Does anyone know when does the performance period begin?
small community adjustment
NC-v4 LTc5:Access to quality transitposted by nancy picard on
For LEED 2009, there was CIR 431 from the CaGBC that adjusted frequency for communities under 50,000 people. Is there a similar adjustment acceptable for LEED v4?
Installation of Lighting Posts
EBOM-v4 MRc3:Purchasing - facility maintenance and renovationposted by Claire Bannister on
We are having two large solar to LED light poles installed in our parking lot. Would this be included in this Facility Maintenance & Renovation credit, as well as "Purchasing- Lamps"?
LEED v4 Requirements documentation
posted by nancy picard on
Hi, I've been searching for LEED v4 Canadian Construction Documents (01 35 21), but the update hasn't been performed yet.
C&S 2009 Office bldg, hotel tenant impact
NC-2009 PIf3:Occupant and Usage Dataposted by James Emery on
We have a 31 storey office tower under construction and slated for substantial in October 2017. It was designed and construction started without any confirmed tenants.
Canadian LEED market
posted by Nirwair Singh Bajwa on
Hi LEED professionals, I found a trend in Canadian LEED registered and certified projects from CaGBC website.
Conformity of commingled facility process
NC-v4 MRc5:Construction and demolition waste managementposted by William Leblanc on
The commingled waste facility that process our project waste work as follows: They weight the container once it arrives from job site, then separate the diffents matrials into percentage of the loa
System Furniture Include or Excluude?
CI-2009 IEQc8.1:Daylight and Views—Daylightposted by Alain Brierley on
I am working on a large 12 story office building that has a 12 story toplite open atrium requiring the credit be documented using option 1.