FTE for university facility

Calculating FTEs
posted by  Nadia Bini  on 

Our project is a University educational facility aiming for LEED-Canada 2009 (v3) certification. LEED stipulates that students are to be considered temporary occupants, however we anticipate that

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Aug 9, 2017, 1:45 pm

LEED v4 CxA

NC-v4 EAp1:Fundamental commissioning and verification
posted by  P. Hardy  on 

In LEED v4, the CxA for Enhanced Commissioning must be independent of the design and construction team- but what if the construction team is also the owner, as in design-build?

2
Sat Aug 5, 2017, 4:25 pm

Green Cleaning as NC ID credit

EBOM-2009 IEQp3:Green Cleaning Policy
posted by  Jordan Kirrane  on 

Hi, I am pursuing Green Cleaning as an ID credit for a NC v3 building. Does anyone know when does the performance period begin?

6
Tue Jul 25, 2017, 3:25 pm

small community adjustment

NC-v4 LTc5:Access to quality transit
posted by  nancy picard  on 

For LEED 2009, there was CIR 431 from the CaGBC that adjusted frequency for communities under 50,000 people. Is there a similar adjustment acceptable for LEED v4?

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Fri Jul 21, 2017, 1:18 pm

Installation of Lighting Posts

EBOM-v4 MRc3:Purchasing - facility maintenance and renovation
posted by  Claire Bannister  on 

We are having two large solar to LED light poles installed in our parking lot. Would this be included in this Facility Maintenance & Renovation credit, as well as "Purchasing- Lamps"?

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Thu Jul 6, 2017, 6:58 pm

LEED v4 Requirements documentation

LEED Canada Forum
posted by  nancy picard  on 

Hi, I've been searching for LEED v4 Canadian Construction Documents (01 35 21), but the update hasn't been performed yet.

6
Default Avatar
President
Solterre Inc.
LEEDuser Premium Member
47 thumbs up
Thu Jun 29, 2017, 8:01 pm

C&S 2009 Office bldg, hotel tenant impact

NC-2009 PIf3:Occupant and Usage Data
posted by  James Emery  on 

We have a 31 storey office tower under construction and slated for substantial in October 2017. It was designed and construction started without any confirmed tenants.

3
Principal
Iredale Architecture
LEEDuser Basic Member
0 thumbs up
Wed Jun 7, 2017, 5:06 pm

Canadian LEED market

LEED Canada Forum
posted by  Nirwair Singh Bajwa  on 

Hi LEED professionals, I found a trend in Canadian LEED registered and certified projects from CaGBC website.

3
Architect Partner
Provencher Roy Architectes
LEEDuser Basic Member
2 thumbs up
Fri May 26, 2017, 3:04 pm

Conformity of commingled facility process

NC-v4 MRc5:Construction and demolition waste management
posted by  William Leblanc  on 

The commingled waste facility that process our project waste work as follows: They weight the container once it arrives from job site, then separate the diffents matrials into percentage of the loa

2
Director of FM Integration and Sustainability
Shawmut Design and Construction
LEEDuser Basic Member
21 thumbs up
Mon May 8, 2017, 5:27 pm

System Furniture Include or Excluude?

CI-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Alain Brierley  on 

I am working on a large 12 story office building that has a 12 story toplite open atrium requiring the credit be documented using option 1.