Forum quick links
Indoor plants planted in the ground
NC-2009 SSc5.1:Site development - protect or restore habitatposted by Albert Sagrera on
Good afternoon, We are analyzing a building that in addition to having an outside green area and a green roof, will also have plants planted in the ground inside the building, without flowerpots.
OCCUPANCY TO CALCULATOR
Warehouses-NC-v4 WEc2:Indoor water use reductionposted by Helena Garcia on
Dear Leed users, We are doing a warehouse project in Spain.
Credit Complance/Justification in Spanish
posted by Peter Gibney on
For justifiying compliance with LEED credits for a Project in Spain, can supporting documentation, management plans, etc.
FTE - Healthcare buildings
Healthcare-v2009 PIf3:Occupant and Usage Dataposted by VICTOR MORENO on
In our Healthcare project, there are workers during the morning, afternoon and evening, with a time of 8 hours each. if I count the FTE, I get a total of workers greater to the number of workstati
Facilities and alterations. Outside the building
EBOM-2009 IEQc1.5:Indoor air quality best management practices - indoor air quality management for facility additions and alterationsposted by Mercè Llorca on
There are outside works planned to be done.
Prohibit Smoking Signage in entrance of Parking and loading docs
EBOM-2009 IEQp2:Environmental Tobacco Smoke (ETS) controlposted by Mercè Llorca on
Even though there is a post over this ítem I am not really sure about this two áreas and the need of signage. In our builiding there are 4 entrances to the underground car park.
Lots and open space question
NC-2009 SSc5.2:Site development - maximize open spaceposted by Albert Sagrera on
Hello, We are wondering if a future building occupying two different plots can be considered as a single LEED project or not. In the case that it is considered as a single project, as it affects
Additional Enhanced IAQ Strategies
NC-v4 EQc1:Enhanced indoor air quality strategiesposted by Marina Curto on
In this credit, two options are available, Options 1 and 2. Can a project achieve Option 2 only without pursuing Option 1?
Error in eQUEST in the Perform Compliance Analysis
CS-2009 EAp2:Minimum energy performanceposted by Toni Herena Montull on
Dear all, I am stuck with an error from eQUEST.
Logistic Warehouse
NC-v4 EQc7:Daylightposted by Helena Garcia on
Our project is a logistic warehouse which is divided into two buildings.