Ice machines

NC-v4 WEc4:Water metering
posted by  John Covello  on 

Hello. Are Ice Machines considered process water for the purposes of this credit? If they are connected to a freezer does that count?

1
Tue Mar 29, 2016, 8:09 pm

LPD for manufacturing space

NC-2009 EAp2:Minimum energy performance
posted by  Panupant Phapant  on 

Hi everyone, The project is cosmetic and medicine manufacturing with office. My question is, What difference between detailed manufacturing and Low/High Bay in ASHRAE90.1-2007 table 9.6.1?

1
Fri Sep 23, 2016, 2:49 pm

Alternative HVAC duct sealant

NC-2009 IEQc3.1:Construction IAQ management plan - during construction
posted by  John Covello  on 

Hi, My contractor is proposing and alternative method to sealing the air conditioning ducts. They would like to use a foam for the duct end that would be air tight.

1
Wed Nov 19, 2014, 6:19 pm

Motorbike, motocycle & Scooter parking count towards SS CR 4.4?

NC-2009 SSc4.4:Alternative transportation - parking capacity
posted by  John Covello  on 

Hello everyone, I see in earlier posts that it is unclear if motorbike, scooters & motorcycles parking counts towards this credit's total or not.

1
Fri Oct 30, 2015, 8:09 am

Project size extended in the middle of construction

NC-2009 MPR4:Must comply with minimum floor area requirements
posted by  wachira sosaeng  on 

My project registered for LEED 2009, mixed use building with 2 towers on the same podium.

1
Sat Aug 26, 2017, 9:03 pm

100% outdoor air indirect evaporative cooling system

NC-2009 EAp2:Minimum energy performance
posted by  BEE Incorporations  on 

Hi everybody, The project is a garment factory. We are modeling a 100% outdoor air IEC system for the proposed case. And the system 8 (VAV with PFP Boxes) is modeled in the baseline case.

1
Mon Dec 28, 2015, 10:13 am

Actual Operation of Carpool parking

NC-2009 SSc4.4:Alternative transportation - parking capacity
posted by  Jatuwat Varodompun  on 

We have a restaurant apply for LEED NC retail, We have the carpool parkings for both customers abd staffs.

1
Fri Nov 27, 2015, 4:48 am

Zone adjust in residential project

CS-2009 EAp2:Minimum energy performance
posted by  Panupant Phapant  on 

We have an apartment building project. In 1 dwelling unit has 1 bedroom 1 living unit and restroom. Do I need to separate between bedroom and living quarter ?

1
Mon Sep 12, 2016, 1:42 pm
1
Wed Dec 17, 2014, 3:15 pm

Project size extended in the middle of construction

NC-v4 MPR3:Must comply with project size requirements
posted by  wachira sosaeng  on 

My project registered for LEED 2009, mixed use building with 2 towers on the same podium.

1
Tue May 30, 2017, 5:12 pm