Narrative for Option 2 Contractor confimration

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Saud Abdul Rasheed  on 

Hi all, We are not going to provide photos for this credit but we have an IAQ plan developed and the contractor has been following it according to the credit requirement.

1
Mon Oct 26, 2015, 1:54 pm

water cooled chilller

NC-2009 EAp2:Minimum Energy Performance
posted by  sherif el adly  on 

Hi Marcus The building size is mandating to model the baseline with a water cooled chiller and I will compare the baseline with the design which is using HVAC that is (air cooled chiller + ice sto

1
Thu Dec 1, 2016, 5:40 pm

modeling with air cooled chiller

NC-2009 EAp2:Minimum Energy Performance
posted by  sherif el adly  on 

the building size is mandating to model the baseline with a water cooled chiller and I will compare the baseline with the design which is using HVAC that is (air cooled chiller + ice storage + dive

0

smoke leakage test for duct

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Abdulla Anwar  on 

Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test, prior to final air leakage test since the project specs is giving a small allowable 1% from basis of des

1
Sat Aug 26, 2017, 8:59 pm

Gypsum board recycling resource, Saudi Arabia

NC-2009 MRc2:Construction Waste Management
posted by  Shreepad Bandagi  on 

Wondering if anyone would have a resource for gypsum board recycling anywhere in Saudi Arabia. Thanks!

1
Wed Jul 9, 2025, 10:09 am

CxA role

NC-2009 EAc3:Enhanced Commissioning
posted by  Abdulla Anwar  on 

Can you advise the CxA role if it was a part of Owner organization? .......................... by the way what is the commissioning developed plan CxP?

1
Tue Aug 9, 2016, 3:27 pm

Baseline System 2

NC-2009 EAc1:Optimize Energy Performance
posted by  SSN Energy Model  on 

As per Table 6.8.1D, I observed the following EER = 12.3-(0.213*Cap/1000) EER Also, Cap means the rated cooling capacity of the product in Btu/hr.

1
Fri Apr 21, 2017, 2:48 pm

Concrete as Temp barriers

NC-2009 MRc2:Construction Waste Management
posted by  Ahmad Gabir  on 

Hi , We are working on Mega project is Saudi Arabia where we are using the concrete waste to build Safety road/excavation barriers which will be used on site during construction instead of purchasi

1
Tue Nov 29, 2016, 2:05 pm

SSp1 and EPA in KSA

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  FABIO VIERO  on 

We are working on two projects located in Saudi Arabia under LEED 2009 certification. We are looking for finding the appropriate measures to be applied, as per EPA’s Construction General Permit an

0

100% certified wood

NC-2009 IDc1:Innovation in Design
posted by  Abdulla Anwar  on 

Dears, Our project is aiming for innovation design credit of 100% FSC certified wood, my concern is about does (FSC mixed) certified product contributing to this credit or only the (100% FSC) cert

2